Ratification of approved and fully executed Change Order No. 3 reflecting an increase of forty (40) additional construction calendar days, for the project "Mile 9 N. & FM 1015 -Package 1B Improvements-2018 Bond Referendum Project No. 24'', Contract No. C-HCDD1-21-054-01-11 - with Mor-Wil, LLC, as recommended by Project Engineer, Halff Associates, Inc.
BACKGROUND
Completion date as per CO-3 - December 8, 2023
Fiscal Impact