AI - 94438
4.B.
DD-CONSENT AGENDA SPECIAL MTG
Meeting Date:
03/05/2024
Submitted For:
Jaime Salazar
Submitted By:
Justin Silva
Department:
DRAINAGE DISTRICT

Information

CAPTION

Ratification of the approved and fully executed Change Order No. 5, reflecting a decrease in the amount of ($23,682.11) and additional sixty (60) calendar days, for the project "Mid-Valley Airport Ditch 18B Drainage Improvements - 2018 Bond Referendum Project No. 19’', Contract No. C-HCDD1-22-020-05-31, with  Mor-Wil, LLC, as recommended by Project Engineer, B2Z Engineering, LLC., and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.