AI - 94786
7.B.
DD-REGULAR AGENDA SPECIAL MTG
- Meeting Date:
- 04/02/2024
- Submitted For:
- Omar Anzaldua Jr.
- Submitted By:
- Linda Martinez
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
1. Requesting approval of the final negotiated Professional Engineering Services Agreement with Javier Hinojosa Engineering in connection with the “Weslaco North Lateral – 2023 Bond Referendum Project No. 10”, Contract No. C-HCDD1-24-018-04-02 as approved for negotiations on 03/05/2024, AI 94429 (subject to final legal review).
2. Acceptance and approval of Work Authorization No. 1 for Project 1 in the amount of $255,620.00, as submitted by Javier Hinojosa Engineering through Contract No. C-HCDD1-24-018-04-02 to provide Professional Engineering Services for the “Weslaco North Lateral – 2023 Bond Referendum Project No. 10” (subject to final legal review).
2. Acceptance and approval of Work Authorization No. 1 for Project 1 in the amount of $255,620.00, as submitted by Javier Hinojosa Engineering through Contract No. C-HCDD1-24-018-04-02 to provide Professional Engineering Services for the “Weslaco North Lateral – 2023 Bond Referendum Project No. 10” (subject to final legal review).
BACKGROUND
Fiscal Impact
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 03/28/2024 03:23 PM |
- Form Started By:
- Linda Martinez
- Started On:
- 03/28/2024 02:45 PM
- Final Approval Date:
- 03/28/2024