CAPTION
Requesting acceptance and approval of Change Order No.3 from Mor-Will, LLC for the "[ARPA-22-124-096] - Hidalgo County Precinct 4 North Main Drain II Stormwater Project" (C-23-0261-08-22-10), for a 90-day time extension and total project amount increase of $431,953.43, as recommended by the Project Engineer, L&G Consulting Engineers, Inc.
BACKGROUND
Fiscal Impact
- CALENDAR YEAR:
- 2024
- ACCT. #:
- 4-1290-431-50-115-283-4-723
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
--Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | Ignacio Amezcua | 06/07/2024 04:33 PM |
| Budget and Management | Veronica Ortiz | 06/07/2024 04:33 PM |
| Final Approval | Monica Salinas | 06/07/2024 05:30 PM |
- Form Started By:
- Victor Borrego
- Started On:
- 06/04/2024 10:42 AM
- Final Approval Date:
- 06/07/2024