CAPTION

Discussion, consideration and authorization for approval to move an existing 30" high pressure gas line that crosses Tower Road between Moore Road on the north and El Gato Road on the south. 

BACKGROUND

See attached letter and field notes for the parcel indicated from engineer.
The work would be done by Spectra Energy (formerly known as Texas Eastern Transmission, LP) and will take approximately 2 days to complete once approved by Hidalgo County. Spectra Energy has estimated construction for the extension of the existing vents will be approximately $8,250.00.

Fiscal Impact

FISCAL YEAR:
ACCT. #:
8-1202-431-00-122-027-0-731
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Available balance is $12,264.12 as of 6/3/08.

Attachments

Form Review

Inbox Reviewed By Date
Budget and Management Dina Trevino 06/03/2008 08:28 AM
Auditor's Office lfong 06/05/2008 08:09 AM
Purchasing / Internal msalazar 06/05/2008 04:49 PM
Court Administrator Alejandro Garcia 06/06/2008 08:22 AM
Form Started By:
ycisneros
Started On:
06/02/2008 03:57 PM
Final Approval Date:
06/06/2008