Ratification of approved and fully executed Change Order No.2, reflecting an increase in the amount of $9,733.02 and (30) additional days for the project ''North Main Drain Expansion (Canton to 17 1/2) TDEM'', Contract No. (C-HCDD1-22-066-05-02), with Welch Excavation and Utility Company Inc., as recommended by Project Engineer, B2Z Engineering, LLC and and approved by HCDD1 District General Manager, Raul E. Sesin, P.E., CFM.