AI- 96264
Budget and Management 13.D.
CC CONSENT AGENDA SPECIAL MTG
Other
- Meeting Date:
- 08/20/2024
- Submitted For:
- Velinda Reyes
- Submitted By:
- Angélica M. Tapia
- Department:
- BUDGET & MANAGEMENT
Information
CAPTION
TXDOT - Pct 4 HSIP - Left & Right Turn Lanes (4 Intersections) (1315) Revised Order:
Rescind the order approved with AI-85382 on 5/28/24 regarding the CCSJ #0921-02-525 road project and approval of the revised order 96264 as requested by TXDOT.
Rescind the order approved with AI-85382 on 5/28/24 regarding the CCSJ #0921-02-525 road project and approval of the revised order 96264 as requested by TXDOT.
BACKGROUND
CCSJ#0921-02-525
OFF-SYSTEM
TXDOT NOW REQUIRES FOR ALL AFA AND RELATED AMENDMENTS TO BE SIGNED THROUGH DOCUSIGN.
AFA AND ORDER APPROVED WITH AI-95382 CC 5/28/24. ORDER IS BEING REVISED AS REQUESTED BY TXDOT LEGAL TEAM.
OFF-SYSTEM
TXDOT NOW REQUIRES FOR ALL AFA AND RELATED AMENDMENTS TO BE SIGNED THROUGH DOCUSIGN.
AFA AND ORDER APPROVED WITH AI-95382 CC 5/28/24. ORDER IS BEING REVISED AS REQUESTED BY TXDOT LEGAL TEAM.
Fiscal Impact
- CALENDAR YEAR:
- 2024
- ACCT. #:
- 4-1XXX-431-00-124-238-0-XXX
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
FUNDS AVAILABLE AS OF 8/13/24.TXDOT 100% CONSTRUCTION COST PARTICIPATION ($786,291). ANY COST OVERRUNS IS THE RESPONSIBILITY OF THE COUNTY.
COUNTY 100% ENGINEERING & ENVIRONMENTAL COST PARTICIPATION.
COUNTY DIRECT STATE COSTS $46,255.
($20,045 INITIAL PAYMENT / $26,210 PAYMENT DUE 60 DAYS PRIOR TO THE DATE SET FOR RECEIPT OF THE CONSTRUCTION BIDS).
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Ortiz | 08/09/2024 03:58 PM |
| Budget and Management | Veronica Ortiz | 08/14/2024 04:59 PM |
| Final Approval | Monica Salinas | 08/16/2024 05:53 PM |
- Form Started By:
- Angélica M. Tapia
- Started On:
- 08/08/2024 01:08 PM
- Final Approval Date:
- 08/16/2024