AI - 97334
6.E.
DD-REGULAR AGENDA SPECIAL MTG
- Meeting Date:
- 11/12/2024
- Submitted For:
- Omar Anzaldua Jr.
- Submitted By:
- Justin Silva
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Requesting approval of Change Order No. 1, reflecting an increase in the amount of $70,000.00 and 122 additional construction calendar days for the project ''Ditch W-01-00 Gate Structure Improvements'', Contract No. (C-HCDD1-23-008-04-04), with Mor-Wil, LLC, as recommended by Project Engineer, Assistant District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 11/08/2024 04:26 PM |
- Form Started By:
- Justin Silva
- Started On:
- 11/06/2024 08:07 AM
- Final Approval Date:
- 11/08/2024