CAPTION
Ratification of approved and fully executed Change Order No.1, reflecting and increase in the amount of $21,357.46 and 60 additional construction calendar days for project ''365 Toll Off-Site Drainage Improvements Project Outfall 2, 3 & 4'', Contract No. C-HCDD1-23-042B-04-16, with RBM Contractors, LLC, as recommended by Project Engineer B2Z Engineering and approved by District General Manager, Raul E. Sesin, PE, CFM