CAPTION

Requesting acceptance and approval of Change Order No. 9 from REIM Construction Inc. for the "Construction of Mile 3 N Rd Project (From Gill to FM 492)" (C-20-294-02-23) for a total project decrease of $256,426.74, as recommended by the Project Manager, B2Z Engineering, LLC. 

BACKGROUND

The stated amount will be credited to the county.

Fiscal Impact

CALENDAR YEAR:
2025
ACCT. #:
FUNDS AVAILABLE Y/N?:
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

No budgetary impact, project total was decreased.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal Ignacio Amezcua 01/24/2025 04:02 PM
Budget and Management Veronica Ortiz 01/24/2025 04:05 PM
Final Approval Monica Salinas 01/24/2025 05:50 PM
Form Started By:
Juan Herrera
Started On:
01/22/2025 02:42 PM
Final Approval Date:
01/24/2025