Skip to main content

AgendaQuick™

View Agenda Item

AI - 99094
4.B.
DD-CONSENT AGENDA SPECIAL MTG
Meeting Date:
04/15/2025
Submitted For:
Omar Anzaldua Jr.
Submitted By:
Justin Silva
Department:
DRAINAGE DISTRICT

Information

CAPTION

Ratification of approved and fully executed Change Order No.2, reflecting 50 additional days for the project ''Pharr-McAllen Lateral East - 2023 Bond Project No. 9'', Contract No. C-HCDD1-24-029-06-11, with Synergy Development & Construction, LLC., as recommended by Project Engineer GDJ Engineering, LLC and approved by District General Manager, Raul E. Sesin, PE, CFM

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 04/11/2025 04:02 PM
Form Started By:
Justin Silva
Started On:
04/10/2025 03:38 PM
Final Approval Date:
04/11/2025