CAPTION
Ratification of approved and fully executed Change Order No.1, reflecting 117 additional days for the project ''South Main Drain Channel Improvements Phase 2 - 2023 Bond Project No. 3'', Contract No. C-HCDD1-24-007-03-19, with Econ Group, LLC., as recommended by Project Engineer Assistant District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM and approved by District General Manager, Raul E. Sesin, PE, CFM