CAPTION
Ratification of approved and fully executed Change Order No.2, reflecting an increase in the amount of $36,800.00 and an additional 30 construction calendar days for the project ''Mission-McAllen Drain Phase 3 -2023 Bond Referendum Project No. 12'', Contract No. C-HCDD1-24-032-07-09, with Synergy Development & Construction, LLC, as recommended by Project Engineer, SAMES, Inc. and approved by Assistant District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM.
BACKGROUND
Project end date as per change order 2: 6/26/2025