CC CONSENT
COMMISSIONERS' COURT MEETING
NOTICE is hereby given in accordance with Chapter 551, Texas Government Code, that a REGULAR MEETING of the Commissioners' Court will be held in the Commissioners' Courtroom of the Administration Building, 100 E. Cano, 1st floor, Edinburg, Hidalgo County, Texas. Discussion and possible action relating to the following business will be transacted:
NOTICE TO THE PUBLIC
CONSENT AGENDA
The following items are of a routine or administrative nature. The Commissioners' Court has been furnished with background and support on each item, and/or it has been discussed at a previous meeting. All items will be acted upon by one vote without being discussed separately unless requested by a Commissioner, in which event the item or items will immediately be withdrawn for individual consideration in its normal sequence after the items not requiring separate discussion have been acted upon. The remaining items will be adopted by one vote.
1. Freedom Acres L12 (Sioux NS/E Hutto)- Andres Pecero- BORE- 3/4" service connection
2. Heidelberg L171 (NWC 2E/9N)Maria Moreno- BORE- 3/4" service connection
3. Approximately 500' south of mile 20N on the east side of Engleman Rd- Victor H. Resendez- X Rd- 3/4" service connection
4. Approximately 1/4 mile west of FM 1015 on the north side of mile 15 1/2 N- Isaac Rodriguez- BORE- 3/4" service connection
El Paso E & P Company, L.P.:
5. One 3" welded steel pipeline crossing Iowa Rd 3,650 ft north of Mile 12 Rd, running diagonally 72ft across Iowa Rd from Lot 12, Block 37 Texan Gardens S/D into lot 12, Block 38 Texan Gardens S/D.
Quintanilla, Headley and Assoc.:
6. The contractor proposes to install a 30" RCP storm sewer line 5.0' East of the west R.O.W. line of an opened county road. The county road is 2600.0' west of FM 88 on mile 20 North road from there the 30" RCP. Line will run south for 3700.0' to an exist drain ditch.
7. The contractor proposes to install a 18" RCP storm sewer line 5.0' east of the west ROW line of an opened County Road. The county road is 2500.0' west of FM 88 on Mile 21 North road from there the 18" RCP will run north 2400.0' to an existing drain ditch.
8. The contractor proposes to install a 24" RCP storm sewer line 5.0' south of the north ROW line of mile 20 North road. The 24" RCP line will start 1300.0' east of mile 5 1/2 road and then run east for 1500.0' to a proposed type "CC" Inlet.
Occupied Housing Rehabilitation Program.
|
Requisition
|
Vendor
|
Department
|
Amount
|
Account Number
|
|
119876
|
Dell
DIR-SDD-192 |
ROW
|
$1,074.75
|
7-1200-431-00-260-001-0-745
|
CDW Government, Inc. - TCPN #4713