AGENDA DRAINAGE DISTRICT BOARD OF DIRECTORS FEBRUARY 20, 2024 9:30 A.M. |
|
NOTICE is hereby given in accordance with Chapter 551, Texas Government Code, that a SPECIAL MEETING of the Drainage District #1 Board of Directors will be held in the Commissioners Courtroom of the Courthouse Annex III Building, 100 E. Cano, 1st floor, Edinburg, Hidalgo County, Texas. The Board of Directors may, at any time during this meeting, retire to a closed meeting pursuant to §551.071(2) of the Texas Government Code to seek the advice from its attorney on any subject slated for discussion or action on the agenda. Discussion and possible action relating to the following business will be transacted:
In accordance with Section 551.127, NOTICE is hereby given that a physical quorum, including the presiding officer/member, will be present at the specified meeting location. Some members of the governing body and/or government officials may participate via videoconference.
Members of the public are encouraged to watch the meetings online, at: www.hidalgocounty.us/HClive
2. Requesting approval of Resolution in support of Joint Request by Hidalgo County and Hidalgo County Drainage District No.1 for FY25 Community Project Funding (CPF) for the West Main Drain Expansion Project. (Subject to final legal review)
| FIRM NAME | SCORE | RANK |
| NM CONTRACTING, LLC | 99.33 | |
| ECON ENRIQUEZ CONSTRUCTION, LLC | 88.91 | |
| RG ENTERPRISES, LLC | 86.80 | |
| TRIGEN CONSTRUCTION, LLC | 83.63 | |
| CELSO GONZALEZ CONSTRUCTION | 80.35 | |
| HOLCHEMONT, LTP | 73.47 |
2. Pursuant to the Boards approval requesting authority for Hidalgo County Drainage District No.1 to negotiate a Construction Contract with the number one ranked firm of: __________________________, for construction services for the "HCDD1 Complex -M&O Training Facility."
2. Pursuant to the Board's Approval of the Professional Engineering Services Agreement with R.R.P. Consulting Engineers, LLC, requesting approval of Work Authorization No. 1 in the amount of $139,583.00, to provide Professional Engineering Services for "Raymondville Drain Outfall System", subject to final legal review (Contract # C-HCDD1-24-012-02-20).
3. Requesting approval of Work Authorization No. 2 in the amount of $1,721,005.26, to provide ASA Feasibility Study for "Raymondville Drain Outfall System", subject to final legal review.
2. Requesting authority for Hidalgo County Drainage District No. 1 to negotiate a Professional Engineering Services Agreement, with Halff Associates Engineering, from the District Pre-approved "Pool of Pre-qualified Professional Engineers", as approved by the Board of Directors on March 07, 2023 (AI 89829) as it relates to the update of the Hidalgo County Drainage District No. 1 Hazard Mitigation Action Plan.
1. Professional Engineering Services -RFQ No. HCDD1-24-001-03-13-JS
2. Professional Surveying Services -RFQ No. HCDD1-24-002-03-13-ESZ
2. Pursuant to TXLGC 262.031 (b), requesting authority/approval for Drainage District General Manager, Raul E. Sesin, P.E., CFM, to execute change orders that involve an increase or decrease in cost of $50,000.00 or LESS and in no event to exceed the Change Order's statutory limits. The original contract price may not be decreased by 18 % or more without the consent of the contractor.
1. Approval of Application for Payment No. 8 in the amount of $21,600.00 from RBM Contractors pertaining to Construction Contract C-HCDD1-22-051-01-17. Project Engineer HCDD1 Yvette Barrera, PE, CFM PO#647299
Mile 9 N. & FM 1015 Package 1B - Budget 524
2. Approval of Application for Payment No. 7 in the amount of $96,734.89 from Mor-Wil, LLC pertaining to Construction Contract C-HCDD1-21-054-12-08. Project Engineer Halff Associates PO#645350
Mission McAllen Rado Alternate - Budget 525
3. Approval of Application for Payment No. 15 in the amount of $172,890.00 from Gonzalez Engineering pertaining to Construction Contract C-HCDD1-21-023-07-27. Project Engineer B2Z Engineering PO#642887
South I Rd - Budget 533
4. Approval of Application for Payment No. 3 in the amount of $74,338.20 from Mor-Wil, LLC pertaining to Construction Contract C-HCDD1-22-060-11-29. Project Engineer B2Z Engineering PO#647343
2. Acceptance and approval of Work Authorization No. 1 in the amount of $98,919.10, as submitted by Izaguirre Engineering Group, LLC through Contract No. C-HCDD1-24-009-02-20 to provide Professional Engineering Services for "PD Lateral Drain Extension 5 – 2023 Bond Referendum Project No. 15" (subject to final legal review).
1. Payment approval of Invoice No. 18-21-2023 RD in the amount of $207,259.79 from Hidalgo County Precinct 4 for Pay Periods 18 through 21, 2023.
2. Payment approval of Invoice No. 18-21-2023 RD in the amount of $76,045.81 from Hidalgo County Precinct 4 for Pay Period 22, 23, and 25, 2023.
Board of Directors may go into Closed Session pursuant to Subchapter D of Chapter 551 of the Texas Government Code to discuss the following:
a) Pending or Contemplated Litigation: b) a Settlement Offer: or c) a Matter in Which the Duty of the Attorney to the Hidalgo County Drainage District No. 1 under the Texas Disciplinary Rules of Professional Conduct of the State Bar of Texas Clearly Conflicts with Chapter 551 of the Texas Government Code (Tex. Gov't. Code 551.071)