CONSENT AGENDA DRAINAGE DISTRICT BOARD OF DIRECTORS OCTOBER 28, 2025 1:30 P.M. |
NOTICE is hereby given in accordance with Chapter 551, Texas Government Code, that a SPECIAL MEETING of the Drainage District #1 Board of Directors will be held in the Commissioners Courtroom of the Courthouse Annex III Building, 100 E. Cano, 1st floor, Edinburg, Hidalgo County, Texas. The Board of Directors may, at any time during this meeting, retire to a closed meeting pursuant to §551.071(2) of the Texas Government Code to seek the advice from its attorney on any subject slated for discussion or action on the agenda. Discussion and possible action relating to the following business will be transacted:
NOTICE TO THE PUBLIC
CONSENT AGENDA
The following items are of a routine or administrative nature. The Drainage District #1 Board has been furnished with background and support on each item, and/or it has been discussed at a previous meeting. All items will be acted upon by one vote without being discussed separately unless requested by a Board Member, in which event the item or items will immediately be withdrawn for individual consideration in its normal sequence after the items not requiring separate discussion have been acted upon. The remaining items will be adopted by one vote.
AEP Telecom proposes to install one 144-count ADSS fiber optic line at Property ID 246263, located at North Capisallo E 10 AC of South 20AD FT 2227, crossing ditch 2DA (UID 0779), maintained by HCDD1.
AEP Telecom proposes to install one 144-count ADSS fiber optic line at Property ID 246263 North Capisallo E 10 AC of South 20AC FT 2227, crossing Ditch 2D9A (UID 0770), maintained by HCDD1.
AEP Telecom proposes to install one 144-count ADSS fiber optic line at Property ID 246152, located at North Capisallo N1138' – S1240' Blk F FT 2171 34.49 AC Net, crossing HCDD1's East Lateral (UID 1199).
AEP Telecom proposes to install one 144-count ADSS fiber optic line at Property ID 246260, located at North Capisallo BLK 225 20 AC, crossing Ditch 10F (UID 0789), maintained by HCDD1.
AEP Telecom proposes to install one 144-count ADSS fiber optic line at Property ID 122340 15 Blk 109 E 9.64 AC Net located at North Capisallo BL 225 20 AC, crossing GCDD1's Main Flood Water Channel (UID 1320).
AEP Telecom proposes to install one 144-count ADSS fiber optic line at Property ID 606292 North Capisallo 5.45 AC-BLK 2180 ABND R/R PROP crossing Ditch 2D2 (UID 0756), maintained by HCDD1.
Bay Runner Pipeline, LLC and Pumpco, Inc. propose to install one (1) 42-inch gas line, with a maximum pressure of 2,350 PSIG and a minimum pressure of 1,880 PSIG, at WLC-0179.000 (Estate of Terry Harris, Santa Rosa Subdivision, out of Partition Share No. 44) and WLC-0182.000 (MJL Farms, LLC, Jose Narciso Cavazos Survey, A-8), crossing HCDD1's Main Flood Water Channel.
The City of Peñitas and G&G Contractors LLC, doing business as RG Enterprise, propose the installation of one (1) 8-inch sanitary sewer line within a 16-inch steel casing, located south of Diamond Avenue and crossing the HCDD1 Peñitas Drain.
The City of Peñitas and G&G Contractors LLC, doing business as RG Enterprise, propose the installation of one (1) 12-inch water line within a 16-inch steel casing, at Amber Way Rd. crossing the HCDD1 Peñitas Drain.
The City of Peñitas and G&G Contractors LLC, doing business as RG Enterprise, propose the installation of three (3) side-by-side 6x8 concrete box culverts, each measuring 140 linear feet, at the intersection of Peñitas Drain and Amber Way Road, crossing the HCDD1 Peñitas Drain.
2. Requesting approval to exercise the District's sole option to renew/extend the contract for "Storm Drain Pipe (RCP) and Related Items" with Rio Valley Pipe, LLC dba CAPA, for an additional one (1) year, under the same terms, and conditions with an approved price adjustment as stated in the Contract Number C-HCDD1-24-052-10-29. Subject to compliance with HB1295.
1. Payment approval of Invoice No. 50711 in the amount of $6,559.65 from B2Z Engineering for September 2025 services. PO#648927 WA#1
Main Floodwater GLO 2015 - Budget 205
2. Payment approval of Invoice No. 50703 in the amount of $18,160.62 from B2Z Engineering for September 2025 services. PO#647408 WA#1
Main Floodwater GLO 2016 - Budget 206
3. Payment approval of Invoice No. 50704 in the amount of $6,027.58 from B2Z Engineering for September 2025 services. PO#647410 WA#1
Region 15 LRGV Planning Group - Budget 545
4. Payment approval of Invoice No. 10149019 in the amount of $94,992.61 from Halff Associates for services through July 2025. PO#650251
5. Payment approval of Invoice No. 10151138 in the amount of $63,364.92 from Halff Associates for services through August 2025. PO#650251
Payment approval of Invoice No. 10151549 in the amount of $38,003.64 from Halff Associates for August 2025 services. PO#637439 WA#3
1. Payment approval of Invoice No. 12412 in the amount of $2,500.00 from Quintanilla, Headley professional services. PO#651394
Mayberry & Glasscock - Budget 543
2. Payment approval of Invoice No. 25105 in the amount of $6,000.00 from Javier Hinojosa Engineering for September 12 through September 30, 2025. PO#651333
M10N & Baseline - Budget 520
3. Payment approval of Invoice No. 50667 in the amount of $1,852.02 from B2Z Engineering for June 2025 services. PO#648169 WA#1
Southwest Weslaco Phase 3 - Budget 535
4. Payment approval of Invoice No. 50709 in the amount of $4,285.18 from B2Z Engineering for September 2025 services. PO#650062 WA#20
Anaquitas Phase 2 - Budget 508
5. Payment approval of Invoice No. 50710 in the amount of $2,260.67 from B2Z Engineering for September 2025 services. PO#650549 WA#21
1. Payment approval of Invoice No. 50705 in the amount of $1,548.94 from B2Z Engineering for September 2025 services. PO#648592 WA#1
West Main Drain Phase 4 - Budget 714
2. Payment approval of Invoice No. 50706 in the amount of $917.89 from B2Z Engineering for September 2025 services. PO#648591 WA#1
PSJA Drain - Budget 716
3. Payment approval of Invoice No. 50712 in the amount of $4,044.10 from B2Z Engineering for September 2025 services. PO#650077 WA#19
Alamo Expressway Phase 2 - Budget 721
4. Payment approval of Invoice No. 50708 in the amount of $276.82 from B2Z Engineering for September 2025 services. PO#649959 WA#18
West Main Drain III Phase 5 - Budget 714
5. Payment approval of Invoice No. 9124 in the amount of $56,000.00 from Leonel Garza & Associates for Appraisal services. PO#650741
Pharr McAllen Lateral - Budget 709
6. Payment approval of Invoice No. 2025-164 in the amount of $2,992.29 from GDJ Engineering for September 2025 services. PO#648442 WA#1