Request/Subject
Status update regarding flood recovery projects, response activities, and project timelines.
Background Information
Gila County staff continue to work on projects related to flood recovery and mitigation efforts, including stabilization of road embankments and low-water crossings, restoration of the Russell Gulch channel, and other infrastructure protection measures. Staff are actively coordinating with multiple funding agencies, including the Federal Emergency Management Agency (FEMA), Department of Emergency and Military Affairs (DEMA), Natural Resources Conservation Service (NRCS), and Department of Forestry and Fire Management (DFFM).
Evaluation
This Work Session will provide status updates on ongoing and proposed flood recovery projects, including project scope, timelines, funding coordination, and anticipated cash flow impacts to Gila County throughout the duration of the projects.
Conclusion
The NRCS Emergency Watershed Protection (EWP) projects were approved on March 16, 2026, initiating the 220-day project completion timeline.
Recommendation
Receive and discuss status updates regarding flood recovery projects, funding opportunities, project timelines, and associated local share requirements.
Suggested Motion
Information/Discussion regarding the status of flood recovery projects, associated funding resources, and the 220-day completion timeline requirements for NRCS Emergency Watershed Protection projects. (Matt Rencher)