ITEM #: 13.
DATE: 07/18/2022

AI #:814
CITY COUNCIL ACTION REPORT
 
SUBJECT: AMENDMENT NUMBER ONE TO THE INTERGOVERNMENTAL AGREEMENT WITH THE STATE OF ARIZONA FOR THE INSTALLATION OF INTELLIGENT TRANSPORTATION SYSTEM EQUIPMENT ALONG LITCHFIELD ROAD FROM MC 85 TO WIGWAM BOULEVARD (PROJECT #42032)
 
STAFF PRESENTER(S): Hugh Bigalk, P.E., City Traffic Engineer

SUMMARY

Amending Intergovernmental Agreement (IGA 20-0007782-I with the Arizona Department of Transportation (ADOT) that provided funding for the purchase and installation of Intelligent Transportation System (ITS) Equipment along Litchfield Road from MC 85 to Wigwam Boulevard.

Recommendation

Approve Amendment One to the Intergovernmental Agreement, IGA 20-0007782-I, A.G. Contract No. P0012020001488 with the Arizona Department of Transportation, Project Location/Name Litchfield Road ITS. (Hugh Bigalk, P.E., City Traffic Engineer)

FISCAL IMPACT

Table 1 below sets forth the original expected project costs, including the city’s obligations for such costs and the revised project costs, including the city’s obligations for such costs.  As reflected in Table 1, since the original IGA was executed, the estimated procurement costs increased from $517,100 to $728,543.  At the city’s request, MAG Regional Council approved additional federal funds in the amount of $199,485 on March 23rd, 2022 with an additional $12,058 city match.  Based on the revised estimate and the additional federal funding awarded for the project, the procurement costs will be funded with $687,016 in federal funds with a $41,527 (5.7% of $728,543) city match. 
Table 1: Project Costs
  Prior Funding
(Approved Fall 202)
Current Funding
(FY2022)
Phase Federal City Total Federal City Total
ADOT Plan Review $0 $30,000 $30,000 $0 $30,000 $30,000
Design $0 $6,000 $6,000 $0 $6,000 $6,000
Procurement $487,531 $29,469 $517,100 $687,016 $41,527 $728,543
Total $487,531 $65,469 $553,100 $687,016 $77,527 $764,543

The net result of the increase in the estimated procurement costs and the additional federal funding is the city’s match obligation for the procurement phase of the project has increased from $29,469 to $41,527.  Because the city has paid $149,620 towards the procurement costs, following the execution of this Amendment, the City will be entitled to a reimbursement of $108,093 ($149,620 - $41,527).

BACKGROUND AND PREVIOUS ACTIONS

On November 16th, 2020 (CAR #2020-7038), the city entered into an IGA with the State of Arizona for the purchasing and installation of ITS equipment along Litchfield Road from MC 85 to Wigwam Boulevard.

STAFF ANALYSIS

Since the original IGA was executed in the fall of 2020, the estimated procurement costs increased from $517,000 to $728,543.  Amendment One amends the cost estimate and modifies the original IGA to reflect the additional federal and city funding for the project.
 