ITEM #: 19.
DATE: 10/24/2022

AI #:819
CITY COUNCIL ACTION REPORT
 
SUBJECT: INTERGOVERNMENTAL AGREEMENT WITH THE STATE OF ARIZONA FOR THE INSTALLATION OF INTELLIGENT TRANSPORTATION SYSTEM EQUIPMENT ALONG COTTON LANE FROM YUMA ROAD TO LILAC STREET (CIP PROJECT #42064)
 
STAFF PRESENTER(S): Hugh Bigalk, P.E., City Traffic Engineer

SUMMARY

Intergovernmental Agreement (IGA 22-0008636-I) with the Arizona Department of Transportation (ADOT) establishing responsibility for funding, purchasing and installation of the Intelligent Transportation System (ITS) Equipment along Cotton Lane from Yuma Road to Lilac Street.

Recommendation

Approve and authorize the Mayor or designee to execute Intergovernmental Agreement, IGA 22-0008636-I, A.G. Contract No. P0012022000989 with the Arizona Department of Transportation, establishing responsibility for funding, purchasing and installing Intelligent Transportation System Equipment along Cotton Lane from Yuma Road to Lilac Street. (Hugh Bigalk, P.E., City Traffic Engineer)

FISCAL IMPACT

The original project cost consisting of ADOT Plan Review, design and procurement is illustrated below in Table 1.  It includes a total federal funding contribution from the Maricopa Association of Governments (MAG) of $87,228 and city funds in the amount of $5,272 for total project cost of $133,000.

Table 1: Project Costs
  Funding Sources
Phase Federal City Total
ADOT Plan Review $0 $30,000 $30,000
Design $0 $10,500 $10,500
Procurement $87,228 $5,272 $92,500
Total $87,228 $45,772 $133,000

Table 2 below provides the planned start and completion dates for the project.

Table 2: Project Schedule
Phase Start End
Design September 2022 March 2023
Procurement April 2023 March 2024

 

BACKGROUND AND PREVIOUS ACTIONS

Staff presented this project as part of the Transportation Priorities to Council (AI-660) at the work session on March 21, 2022.  The project was added to the FY2023-27 CIP as project number 42064.

STAFF ANALYSIS

In August 2021, the MAG issued a call for qualified ITS Projects. The City submitted four projects for consideration and they were selected to proceed using Congestion Mitigation and Air Quality (CMAQ) funds. MAG Regional Council approved the projects in January 2022.

The project will replace existing outdated traffic signal controllers, video detection equipment and vehicle travel time hardware at three intersections along Cotton Lane. The new traffic signal controllers and video detection systems will modernize traffic signals in the city by providing enhanced performance and diagnostic information to the City’s Traffic Management Center (TMC). Installation of the vehicle travel time hardware will allow TMC staff to measure performance of the coordinated arterial roadways, report their performance, and evaluate/adjust traffic signal coordination based on how traffic is moving along Cotton Lane.

Payment of $30,000 for Project Development Administration (PDA) costs plus the City’s matching funds of $5,272 for equipment costs are due to ADOT 30 days after execution of the IGA. Design of the project will be performed by City of Goodyear staff and the environmental documentation will be performed by a consultant which is estimated to cost $10,500.  The city will coordinate with ADOT during the procurement of the equipment.  All equipment will be installed by city staff and reimbursed by ADOT for the federal fund contribution for the project. The project is scheduled to take place in FY2023 with an estimated cost of $133,000, which includes $87,228 of federal funding which will be reimbursed by ADOT. Completion of the project is anticipated to be completed by April 2024. If the PDA costs or overall project costs exceed the initial estimates, the city will be responsible for any additional costs above the initial estimates. The total project cost does not include city labor to install equipment.