| ITEM #: 9. DATE: 12/15/2025 AI #:2873 |
![]() |
CITY COUNCIL ACTION REPORT
| SUBJECT: | RESOLUTION ADOPTING A FOUR-YEAR WATER, WASTEWATER, AND SOLID WASTE RATE PLAN |
| STAFF PRESENTER(S): | Ryan Bittle, Finance Manager |
SUMMARY
Conduct a public hearing on Resolution No. 2025-2499 and consider adoption of a four-year Water, Wastewater and Solid Waste rate plan (2026-2029).
STRATEGIC PLAN ALIGNMENT
![]() |
RECOMMENDATION
ADOPT RESOLUTION NO. 2025-2499 ADOPTING THE PROPOSED FOUR-YEAR WATER, WASTEWATER AND SOLID WASTE RATE STRUCTURES AND PROVIDING FOR EFFECTIVE DATES. (Ryan Bittle, Finance Manager)
FISCAL IMPACT
The proposed four-year rate structure will allow the city to fund operations, capital projects, debt service, and all other costs of service associated with providing water, wastewater, and solid waste services. The FY2026 adopted budget is based on the current five-year rate plan which ends in December 2025.
BACKGROUND AND PREVIOUS ACTIONS
Utility Rate Study
Rate studies are conducted in order to develop a plan or framework to obtain the revenues needed to fund city utility operations while at the same time minimizing the impact of any adjustments on ratepayers. A rate study provides information to citizens and the Council regarding the impact of policy choices on ratepayer monthly bills and the utility's financial health. The city currently has fees in place to support the city's Water, Wastewater, and Solid Waste utility programs and services.Willdan Financial Services, who has provided financial, rate, and capital planning solutions for communities nationwide for over 30 years, performed the city’s utility rate study. Objectives of the rate study included analyzing and making recommendations for rate adjustments, fees, and charges for Water, Wastewater, Solid Waste, and Stormwater utilities to obtain revenues needed to fund operations, maintenance, debt service, asset replacement and capital projects that are not supported by development fees or developer contributions. Willdan finalized its rate studies for Water, Wastewater, and Solid Waste Attachments B & C.
Citizen Water Advisory Committee (CWAC)
City Council
Statutory Compliance
A.R.S. §9-511.01 requires that for any proposed increase in Water or Wastewater rates or rate components, fees, or service charges, the city must adopt a notice of intention and file a written report with data supporting the increase in the Clerk’s Office at least sixty (60) days prior to a public hearing. On September 22, 2025, Council adopted a notice of intent and set December 15, 2025, as the public hearing date which began the state required public process for the adoption of all proposed rates and fees. The adopted notice of intent was posted on the city’s website on September 25, 2025; a copy of the full rate study, including cash flow projections, was posted to the city's website on October 31, 2025; and a copy was filed in the Clerk's office on November 6, 2025; all at least thirty (30) days before the public hearing. Notice of intent to increase rates was subsequently published in the Arizona Business Gazette - Republic Edition newspaper greater than twenty (20) days before the public hearing date. The city is in compliance with all additional requirements as outlined in A.R.S. §9-511.01 not otherwise mentioned.Customer Outreach
The city has taken additional steps above those required by state statute to notify and engage the public during the rate-setting process. Those actions taken are listed below:
- Involvement of the CWAC from April 2025 to September 2025;
- Three (3) public discussions with City Council on proposed rate increases: September 15, 2025, Work Session, October 21, 2025, Council Retreat, and the November 17, 2025, Council Meeting;
- Notice to customers of the proposed rate increases on utility bills in November 2025 and December 2025;
- Notice to customers of the proposed rate increases via the city's various social media channels;
- A frequently asked questions flyer posted both on the city's website and shared via social media; and
- An article in the city's December 2025 InFocus magazine on the recommended rate increases.
STAFF ANALYSIS
The last modification to the city’s utility rate structure was a five-year plan adopted on January 25, 2021, which included rate increases implemented every January from 2021 through 2025. The current proposed plan is anticipated to be effective no earlier than thirty (30) days after adoption of Resolution No. 2025-2499, included as Attachment A.
Proposed Rate Plan:
Average customer bill and impact under the newly proposed four-year plan
Proposed Rate Plan:
Average customer bill and impact under the newly proposed four-year plan
|
Residential
|
2026
|
2027
|
2028
|
2029
|
Avg Monthly Usage |
|
Water
|
$2.71
|
$2.90
|
$3.09
|
$3.30
|
7,500 gallons |
|
Wastewater
|
$3.97
|
$4.18
|
$4.41
|
$4.66
|
6,000 gallons |
|
Solid Waste
|
$1.82
|
$1.97
|
$2.13
|
$2.30
|
flat fee |
| TOTAL MONTHLY BILL IMPACT* | $8.50 | $9.05 | $9.63 | $10.26 | |
|
TOTAL MONTHLY BILL*
|
$155.48
|
$164.53
|
$174.16
|
$184.42
|
|
|
% Increase to Monthly Bill
|
5.8%
|
5.8%
|
5.9%
|
5.9%
|
*Based on average customer usage. Water & Wastewater rates are only applicable to Goodyear residents south of I-10.
Average customer bill and impact under the newly proposed four-year plan
Average customer bill and impact under the newly proposed four-year plan
|
Commercial
|
2026
|
2027
|
2028
|
2029
|
Avg Monthly Usage |
|
Water
|
$35.86
|
$38.28
|
$40.86
|
$43.62
|
65,000 gallons |
|
Wastewater
|
$23.97
|
$25.52
|
$27.17
|
$28.92
|
48,000 gallons |
|
Solid Waste
|
-
|
-
|
-
|
-
|
n/a |
| TOTAL MONTHLY BILL IMPACT* | $59.83 | $63.80 | $68.03 | $72.54 | |
|
TOTAL MONTHLY BILL*
|
$964.72
|
$1,028.52
|
$1,096.54
|
$1,169.10
|
|
|
% Increase to Monthly Bill
|
6.6%
|
6.6%
|
6.6%
|
6.6%
|
*Based on average customer usage. Water & Wastewater rates are only applicable to Goodyear commercial customers south of I-10. Solid Waste fees are not currently charged to commercial customers.
Attachments
- Attachment A - Resolution No. 2025-2499 with Exhibit A
- Attachment B - Rate Study Executive Summary
- Attachment C - Rate Study Full Version
- Staff Presentation

.png)