.jpg)
| MEETING DATE: 09/19/2022 |
|
| TO: | HONORABLE MAYOR AND COUNCILMEMBERS |
| FROM: | JIM SADRO, CITY MANAGER By: Elias Saykali, Public Works Director |
| SUBJECT: | APPROVE COOPERATIVE AGREEMENT WITH CITY OF FULLERTON FOR THE HARBOR BOULEVARD CORRIDOR PROJECT, REGIONAL TRAFFIC SIGNAL SYNCHRONIZATION PROGRAM, PROJECT NO. 74-46029
|
RECOMMENDATION:
That the City Council approve a Cooperative Agreement with the City of Fullerton for the Harbor Boulevard Corridor Project, Regional Traffic Signal Synchronization Program, Project No. 74-46029.
DISCUSSION:
As part of the Cooperative Agreement, the City of Fullerton will serve as the lead agency for the Project. The Harbor Boulevard Corridor Project will synchronize approximately twenty-nine (29) traffic signals along Harbor Boulevard from Arbolita Drive in the City of La Habra to the SR-91 freeway interchange in the City of Fullerton. The approximate 6.4 mile project will improve six (6) traffic signals in La Habra, nineteen (19) traffic signals in Fullerton, and four (4) traffic signals controlled by the California Department of Transportation (Caltrans).
City staff worked collaboratively with the City of Fullerton to develop a Cooperative Agreement for the Project. The Cooperative Agreement identifies the project’s scope of work including engineering design services, construction, signal timing and implementation; in addition, it defines the specific terms, conditions and responsibilities between the City of Fullerton and the City of La Habra.
Staff recommends that the City Council approve and authorize the City Manager to execute the Cooperative Agreement for the Harbor Boulevard Corridor Project Regional Traffic Signal Synchronization Program, Project No. 74-46029.
FISCAL IMPACT/SOURCE OF FUNDING:
GENERAL PLAN RELEVANCE/CITY COUNCIL GOALS & OBJECTIVES:
RN 1.7 – Street System Improvements
RN 1.8 – Safe Street Design
RN 1.9 – Resolve Regional Impacts
RN 1.12 – Signal Coordination
RN 1.14 – Agency Cooperation
ITS 1.1 – Traffic Operations Center
ITS 1.2 – Signal Coordination
ITS 1.3 – Advance Control Technology
ITS 1.4 – Traffic Signal Improvements
ITS 1.5 – Traffic Signal Optimization
Goal 3 - Maintenance and Improvement of City Infrastructure
Objective F - Maintain and upgrade the City's traffic signal system