
Item No. 9.
| MEETING DATE: October 5, 2020 |
|
| TO: | HONORABLE CHAIR AND DIRECTORS |
| FROM: | JIM SADRO, EXECUTIVE DIRECTOR By: Brian Jones, Water Sewer Manager |
| SUBJECT: | APPROVE UPGRADES TO THE LA HABRA UTILITY AUTHORITY'S WATER SYSTEM SUPERVISORY CONTROL AND DATA ACQUISITION SYSTEM FOR WATER TELEMETRY |
RECOMMENDATION:
That the Utility Authority:
A. Approve and authorize an additional $18,400.00 in funding to an existing purchase order with PLCs Plus International, from $67,261.70 to $85,661.70, to perform necessary change orders for the upgrade of the Utility Authority's Supervisory Control and Data Acquisition (SCADA) water telemetry system; and
B. Approve and authorize staff to execute a change order to PLCs Plus International to perform additional work necessary to complete SCADA system upgrades.
A. Approve and authorize an additional $18,400.00 in funding to an existing purchase order with PLCs Plus International, from $67,261.70 to $85,661.70, to perform necessary change orders for the upgrade of the Utility Authority's Supervisory Control and Data Acquisition (SCADA) water telemetry system; and
B. Approve and authorize staff to execute a change order to PLCs Plus International to perform additional work necessary to complete SCADA system upgrades.
DISCUSSION:
On March 16, 2020, the La Habra Utility Authority awarded a contract to PLCs Plus International in the amount of $67,261.70 to implement new SCADA software and to integrate the software with the Utility Authority's water production and treatment facilities. When complete, the upgraded SCADA system will allow staff to:
To complete the Utility Authority's SCADA system upgrade project, it is estimated that an additional 120 hours of engineering and programming will be required, at a cost of $18,400. Staff recommends an increase in funding for this project in the amount of $18,400 and a modification of the existing purchase order to reflect a total funding amount of $85,661.70.
- Control system processes locally or from remote locations
- Monitor, gather, and process data in real-time
- Directly interact with sensors, valves, pumps, and motors through interface software
- Record events into a log file
- Receive alarms remotely for site intrusion, mechanical failures, and other issues
To complete the Utility Authority's SCADA system upgrade project, it is estimated that an additional 120 hours of engineering and programming will be required, at a cost of $18,400. Staff recommends an increase in funding for this project in the amount of $18,400 and a modification of the existing purchase order to reflect a total funding amount of $85,661.70.
FISCAL IMPACT/SOURCE OF FUNDING:
There is no impact to the General Fund. The Fiscal Year 2020-2021 adopted Water Enterprise Operations and Maintenance Fund has sufficient funding to support the additional funding of $18,400 necessary to complete upgrades to the Utility Authority's SCADA system.
GENERAL PLAN RELEVANCE:
WS 1.9 Infrastructure Maintenance