| SUBJECT: | APPROVE NOTICE OF COMPLETION FOR MACY STREET REHABILITATION PROJECT, CITY PROJECT NO. 1-R-23
|
RECOMMENDATION:
That the City Council approve the Notice of Completion for the Macy Street Rehabilitation Project, City Project No. 1-R-23; and authorize staff to submit the Notice of Completion for recordation.
DISCUSSION:
On May 19, 2025, the City Council awarded a construction contract to Copp Contracting, Inc., based in Buena Park, California, in the amount of $469,575. This total includes a 20% contingency for the Macy Street Rehabilitation Project, City Project No. 1-R-23.
The project included pavement reconstruction, installation of a new asphalt Rubber Hot Mix (ARHM) pavement cap, new traffic striping and markings, reconstruction of existing driveway approaches and sidewalks along Macy Street from Whittier Boulevard to North City Limits.
City Staff conducted a final inspection and confirmed that all work was completed in accordance with the project plans, specifications, and standards of the City of La Habra. Following City Council acceptance of the project, staff will file a Notice of Completion (Attachment 1) for recordation at the Orange County Recorder's office.
The project included pavement reconstruction, installation of a new asphalt Rubber Hot Mix (ARHM) pavement cap, new traffic striping and markings, reconstruction of existing driveway approaches and sidewalks along Macy Street from Whittier Boulevard to North City Limits.
City Staff conducted a final inspection and confirmed that all work was completed in accordance with the project plans, specifications, and standards of the City of La Habra. Following City Council acceptance of the project, staff will file a Notice of Completion (Attachment 1) for recordation at the Orange County Recorder's office.
FISCAL IMPACT/SOURCE OF FUNDING:
The final cost of construction for the project was $446,182.67, which is $23,392.33 less than the approved purchase order in the amount of $469,575; therefore, there are sufficient budgeted funds available to cover the cost of the project and to release the retention payment.
GENERAL PLAN RELEVANCE/CITY COUNCIL GOALS & OBJECTIVES:
General Plan Relevance:
RN 1.7 Street System Improvements
RN 1.8 Safe Street Design
AT 3.5 Accessible Facilities
AT 3.5 Street Walkability
AT 3.6 Pedestrian Connectivity
Goals & Objectives:
Goal 3 - Maintenance and improvement of City Infrastructure
Objective C - Maintain streets, alleys, sidewalks, and curb ramps citywide
RN 1.7 Street System Improvements
RN 1.8 Safe Street Design
AT 3.5 Accessible Facilities
AT 3.5 Street Walkability
AT 3.6 Pedestrian Connectivity
Goals & Objectives:
Goal 3 - Maintenance and improvement of City Infrastructure
Objective C - Maintain streets, alleys, sidewalks, and curb ramps citywide