AGENDA RECOMMENDATION |
Consent Calendar 5.G.
City Council Regular Meeting
- Meeting Date:
- 02/09/2026
Agenda Item:
Resolution accepting feasibility report and ordering project for Capital Improvement Project 10839; Public Works Center Welding Bay Exhaust and Tool Replacement.
Recommendation/Action(s):
Adoption of the attached resolution
Summary:
The heating and ventilation systems serving the welding bay within our Public Works Center are aging and in need of replacement. This proposed project includes replacing the welding station rotating ventilation arms, exhaust fans, electrical, and the make-up air unit that serves the welding bay.
Limitations of the existing welding bay heating and ventilation include existing configuration, non-functioning equipment and obsolete equipment. Other limitations include the following:
The estimated costs and funding sources for the project are as follows:
The project was included in the 2026 Facilities Capital Replacement Plan as previously approved by Council.
Staff recommend the Council accept the project feasibility report, order city staff to prepare final plans and specifications, and instruct the City Manager to advertise for bids in accordance with the requirements of law.
Limitations of the existing welding bay heating and ventilation include existing configuration, non-functioning equipment and obsolete equipment. Other limitations include the following:
- Lack of energy conservation capabilities.
- Lack of carbon monoxide and nitrous dioxide sensors.
- Lack of adequate ventilation systems.
The estimated costs and funding sources for the project are as follows:
| ITEM | COST |
| (5) Exhaust Fans | $30,000 |
| (3) Exhaust Arms | $18,000 |
| Make-Up Air Unit | $30,000 |
| Controls (Building Automation System) | $35,000 |
| Installation | $152,000 |
| TOTAL CONSTRUCTION | $265,000 |
| Final Design | $8,500 |
| Construction Contingency | $26,500 |
| TOTAL PROJECT COST | $300,000 |
| FUNDING SOURCE | AMOUNT | PERCENT |
| Facilities Capital | $300,000 | 100% |
| TOTAL FUNDS | $300,000 | 100% |
The project was included in the 2026 Facilities Capital Replacement Plan as previously approved by Council.
Staff recommend the Council accept the project feasibility report, order city staff to prepare final plans and specifications, and instruct the City Manager to advertise for bids in accordance with the requirements of law.