Resolution considering bids for 2026 Sealcoating.

Recommendation/Action(s):

Adoption of the attached resolution.

Summary:

On May 28, 2026, bids were opened for the 2026 Sealcoating project. Three bids were received, with the low bid submitted by Allied Blacktop Company of $566,859.48. The Engineer’s Estimate for the project was $611,964.00.

This year’s area for sealcoating is bound by N Riverfront Drive, Trunk Highway 14, Sakatah Singing Hills State Trail, and CSAH 12.

Staff recommends awarding the construction contract for 2026 Sealcoating to Allied Blacktop Company. The contract has a final completion date of August 28, 2026, and construction is anticipated to start in July.

Staff will provide notice to the community when work is expected to begin once a schedule has been provided by the contractor.