AGENDA RECOMMENDATION |
City Manager's Report 6.B.
City Council Regular Meeting
- Meeting Date:
- 06/22/2026
Agenda Item:
Resolutions authorizing the City Manager and Construction Manager at Risk to solicit bids for the construction of an Air Traffic Control Tower at the Mankato Regional Airport and submitting applications for the current Federal Funding Grant Obligation and future FAA Discretionary Grant Funding.
Recommendation/Action(s):
Adoption of the attached resolutions
Summary:
The funding necessary for design and engineering of the airport tower has been received and was covered by a 100% federally funded grant. On June 1, 2026, the airport tower design and engineering team provided the Issue for Bid/Permit documents finalizing the tower design. Next steps include the Construction Manager at Risk soliciting bids for the construction project.
Construction is estimated to cost $27.7 Million based on the final plans and includes construction administration, controller equipment, airfield lighting regulators, furniture, reimbursable agreement with the FAA, independent cost estimates, and city administration costs.
The City has been awarded $9.765 million in funding for construction.
$3.5 Million – Congressionally Directed Spending (FFY 2026)
$5.0 Million – Federal Contract Tower Program (FFY 2026)
In order to submit the application to obligate the current Federal FCT grant and to apply for the discretionary funding, actual bid amounts are required to be submitted to the FAA. Moving forward with the solicitation for bids does not obligate the City of Mankato to move forward with the project nor does it commit any local dollars to the project. If authorized by the Council, the bids would be advertised as being held for a period up to May 1, 2027, to allow time for additional funding to be sought. The bids would not be awarded until the funding sources have been determined, and the Council authorizes the project to proceed to construction. Below is a proposed schedule for the bidding process and application for discretionary funding.
Proposed Schedule:
The process does deviate from the City’s standard practice of assembling a funding package for the entire project prior to releasing bids. Due to the FAA process, actual bid information is a requirement for both the grant execution for the Federal Contract Tower program and the application for discretionary funding.
With the increased activity at the airport along with safety concerns noted during the air traffic control tower study submitted as part of the FCT application, there is risk associated with not moving the project forward at this time. In consultation with the city attorney and our consultant partners, the plan as proposed is a reasonable and necessary path forward.
Future touchpoints with the council will include the following:
Staff recommend authorizing the City Manager and Construction Manager at Risk to solicit bids for the construction of an Air Traffic Control Tower at the Mankato Regional Airport and submitting applications for the current Federal Funding Grant Obligation and future FAA Discretionary Grant Funding.
Construction is estimated to cost $27.7 Million based on the final plans and includes construction administration, controller equipment, airfield lighting regulators, furniture, reimbursable agreement with the FAA, independent cost estimates, and city administration costs.
The City has been awarded $9.765 million in funding for construction.
$3.5 Million – Congressionally Directed Spending (FFY 2026)
- 95% Federal Funding
- 2.5% State Funding
- 2.5% Local Funding
$5.0 Million – Federal Contract Tower Program (FFY 2026)
- Funds must be obligated by September 1, 2026
- 100% Federal Funding
- Available until June 30, 2028
- 100% State Funding
- Available to cover all local share cost participation.
In order to submit the application to obligate the current Federal FCT grant and to apply for the discretionary funding, actual bid amounts are required to be submitted to the FAA. Moving forward with the solicitation for bids does not obligate the City of Mankato to move forward with the project nor does it commit any local dollars to the project. If authorized by the Council, the bids would be advertised as being held for a period up to May 1, 2027, to allow time for additional funding to be sought. The bids would not be awarded until the funding sources have been determined, and the Council authorizes the project to proceed to construction. Below is a proposed schedule for the bidding process and application for discretionary funding.
Proposed Schedule:
| June 22 | Council Meeting Discussion. |
| June 23 | Release Bids. |
| June 26 | Pre-Bid Meeting. |
| July 14 | Open Bids. |
| July 27 | Guaranteed Maximum Price (GMP) due. |
| July 28 | Share GMP with FAA along with an application for discretionary funding and an FCT grant agreement. |
| September 30 | Receive notification of funding. |
The process does deviate from the City’s standard practice of assembling a funding package for the entire project prior to releasing bids. Due to the FAA process, actual bid information is a requirement for both the grant execution for the Federal Contract Tower program and the application for discretionary funding.
With the increased activity at the airport along with safety concerns noted during the air traffic control tower study submitted as part of the FCT application, there is risk associated with not moving the project forward at this time. In consultation with the city attorney and our consultant partners, the plan as proposed is a reasonable and necessary path forward.
Future touchpoints with the council will include the following:
- Notifications of future funding
- Formal acceptance of future grants
- Upon acceptable funding strategy, formal award of bids through the execution of the GMP amendment with Knutson Construction
Staff recommend authorizing the City Manager and Construction Manager at Risk to solicit bids for the construction of an Air Traffic Control Tower at the Mankato Regional Airport and submitting applications for the current Federal Funding Grant Obligation and future FAA Discretionary Grant Funding.