Skip to main content

AgendaQuick™

View Agenda Item

AGENDA RECOMMENDATION       
Consent Calendar   6.J.
City Council Regular Meeting
Meeting Date:
09/08/2025

Agenda Item:

Resolution considering bids on Capital Improvement Project 11001; Land of Memories Trail.

Recommendation/Action(s):

Adoption of attached resolution.

Summary:

On August 29, 2025, bids were opened on Capital Improvement Project Number 11001. Five bids were received, with the low bid submitted by Nielsen Blacktopping & Concrete, Inc. of $439,552.02. The Engineer’s estimate for the project was $366,275. No alternates were included for the project.
 
The low bid received is approximately 20% above the Engineer’s estimate and upon review it is believed to be largely associated with three items of work. The three items include Prefabricated Modular Block Wall, Service Cabinet, and Install Chain Link Fence. Further review concludes the low bid received for these three items was similar to the other bids received, so we believe the low bid is justified, and the cost was underestimated.
 
Funding for the proposed improvements is shown in the table below. The project was budgeted in the 2025 Capital Improvement Plan and includes funding from both the Minnesota Department of Transportation District 7 Area Transportation Alternatives (TA) program and the Minnesota Department of Natural Resources Regional Trail Program Grant.
 
 
ITEM Bid Award 9/8/25
CONSTRUCTION SUBTOTAL $439,552
Xcel Energy Source of Power $50,000
Construction Contingency $17,590
Administration $26,380
Engineering $43,960
TOTAL PROJECT COST $577,482

SOURCE
 
Transportation Alternatives Grant (1) $249,280
State Trail Grant (DNR) $209.559
Parks Capital (2) $118,643
TOTAL FUNDS $577,482

UNFUNDED AMOUNT
$0

Notes:
(1) State Transportation Improvement Program (STIP) designated $153,065 in FY 25 + $96,215 in FY 26 (advanced to FY 25)
(2) Approximately $1,090,000 Cash Reserve in Parks Capital — Adequate to Fund Remaining Balance
 
Staff recommends awarding the construction contract for Capital Improvement Project Number 11001 to Nielsen Blacktopping & Concrete, Inc. The contract has a substantial completion date for the bituminous trail of November 1, 2025, a final completion date of June 1, 2026, and construction is anticipated to start in September. 

Staff and representatives of the contractor will meet prior to construction to review the work schedule and other miscellaneous items for consideration. 

Attachments