Resolution considering bids on Capital Improvement Project 11217; 2026 Wear Course Paving.
Recommendation/Action(s):
Adoption of attached resolution.
Summary:
On April 16, 2026, bids were opened on Capital Improvement Project Number 11217. Three bids were received, with the low bid submitted by W W Blacktopping, Inc. of $152,498.75. The Engineer’s Estimate for the project was $188,949.00.
Staff recommends awarding the construction contract for Capital Improvement Project Number 11217 to W W Blacktopping, Inc.
The contract has a substantial completion date of August 28, 2026. The project will install the final lift of asphalt pavement on the previously completed CIP project areas:
Staff and representatives of the contractor will notify affected residents prior to installation of the final lift of asphalt pavement.
Staff recommends awarding the construction contract for Capital Improvement Project Number 11217 to W W Blacktopping, Inc.
The contract has a substantial completion date of August 28, 2026. The project will install the final lift of asphalt pavement on the previously completed CIP project areas:
- 11120 – Woodshire Drive
- 11114 – Germania Park Phase 5
- 11078 – W 7th Street