CITY COUNCIL MEMORANDUM
 
City Council Meeting: September 22, 2020
Department: Public Works
Subject: Resolution No. 20-R-106 – Consideration and/or action approving a Resolution by the City Council of the City of Schertz, Texas, authorizing the City Manager to enter into an agreement with Ford Engineering, Inc., for design, bid, and construction phase engineering services for the Aviation Heights Water line relocation project in advance of the Construction project. (C. Kelm/S. Williams/J. Hooks)

BACKGROUND

The City of Schertz Aviation Heights area has under sized water mains that provide limited fire protection and are located in alleyways. The City of Schertz Public works has been working to upgrade and replace these smaller mains with appropriately sized lines to provide an adequate and reliable water supply with better fire protection coverage, as well as relocate these new mains in the front of the homes to increase maintenance efficiencies. Three phases are left that need to be completed in Aviation Heights. Staff desires to design these phases and prepare for construction in FY 20-21.

Ford Engineering is very familiar with this area and has designed the previous phases of waterline improvements and has experience with City utility relocation projects.

Aviation Heights Waterline Relocation Project Budget
Engineering                             $     113,135.00
Construction Contingency       $       11,865.00
Project Total                             $     125,000.00  

Ford Engineering has a Master Professional Services Agreement with the City of Schertz that was awarded based on a competitive Request for Qualifications ("RFQ")

GOAL

To complete the design required for relocation of Aviation Heights water lines..

 

COMMUNITY BENEFIT

The relocation of these lines will improve the service and reliability to the residents in the Aviation Heights service area.
 

SUMMARY OF RECOMMENDED ACTION

Staff recommends that the City Council approve Resolution 20-R-106, authorizing a project agreement with Ford Engineering, Inc., for design, bid, and construction phase engineering services for water relocations in advance of the construction project.
 

FISCAL IMPACT

Funding for the design work is available in the FY 19-20 Water Operating Budget and is included in the FY 19-20 CIP Plan
 

RECOMMENDATION

Staff recommends the City Council approve Resolution 20-R-106, authorizing a project agreement with Ford Engineering, Inc., for design, bid, and construction phase engineering services for waterline relocations in advance of the construction project.
 