Skip to main content

AgendaQuick™

View Agenda Item

AGENDA ITEM REVIEW FORM
3.B.
Special City Council Meeting
Meeting Date:
05/17/2017
Department Head:
Eulogio Vera
Submitted By:
Eulogio Vera, Public Works Director, Public Works Department
Action Requested:
Motion

ITEM:

Discussion and possible action on any and all matters regarding the approval to award the Juan Sanchez Boulevard Reconstruction Project to the lowest responsive bidder. (Eulogio Vera, Public Works Director)

SUMMARY:

The City of San Luis went out to formal bid pursuant to Title 34 of the Arizona Revised Statutes for construction of the Juan Sanchez Boulevard Reconstruction Project between Merrill Avenue and Main Street.  Bids will be received on Monday May 15, 2017.  The project will be funded partially by City Highway Users Revenue Fund and partially by City Wastewater bond funds .  Project duration is to be 120 calendar days, which means that funds will need to be committed in fiscal year 2018 for its completion.

RECOMMENDATION / SUGGESTED MOTION:

I HEREBY MOVE TO AWARD A CONTRACT TO THE LOWEST RESPONSIBLE BIDDER FOR THE JUAN SANCHEZ BOULEVARD RECONSTRUCTION PROJECT FOR AN AMOUNT NOT TO EXCEED $650,000.00

Fiscal Impact

IS THERE FISCAL IMPACT ASSOCIATED WITH THIS ITEM:
Yes
CITY/STATE/FEDERAL FUNDS:
State & City
TOTAL:
TBD
BUDGETED AMOUNT:
$0.00
AVAILABLE AMOUNT TO TRANSFER:
N/A
ACCT NAME & GL#/REMAINING BALANCE BEFORE PURCHASE:
HURF and Wastewater Funds

FISCAL IMPACT STATEMENT (IF THIS IS A BUDGET TRANSFER, YOU MUST ATTACH THE BUDGET ADJUSTMENT FORM):

HURF - GL Acct # 200-210-90010 Capital Outlay - Improvement Roads
Available Amount $702,720
80% of total project cost to be covered by HURF funds

Wastewater - GL Acct # 310-311-90015.350 Capital Water System
Available Amount $1,226,730
20% of total project cost to be covered by WW funds. All related to wastewater infrastructure replacement.