AGENDA ITEM REVIEW FORM |
6.A.
Regular City Council Meeting
- Meeting Date:
- 08/08/2018
- Department Head:
- Jenny Torres
- Submitted By:
- Dania Castillo, Economic Development Assistant, Administration, Economic Development
Action Requested:
Motion
ITEM:
Discussion and possible action on any and all matters regarding the award of a construction contract to DPE Construction, Inc. for pavement of Merrill Avenue Improvements Phase II (CDBG Contract #114-18). (Jenny Torres, Economic Development Manager)
SUMMARY:
The City of San Luis intends to award DPE Construction, Inc. the pavement contract for Merrill Avenue Improvements Phase II (Community Development Block Grant Contract #114-18) in the amount of $291,635.66. The contractor was selected competitively by sealed bids and was the lowest bidder determined to be qualified and capable of performing the contract. The project will be funded by a Community Development Block Grant from the Arizona Department of Housing.
RECOMMENDATION / SUGGESTED MOTION:
I MOVE TO ACCEPT THE BID AND APPROVE THE CONTRACT FOR DPE CONSTRUCTION, INC. FOR THE IMPROVEMENTS ON MERRILL AVENUE AS PRESENTED.
Fiscal Impact
- IS THERE FISCAL IMPACT ASSOCIATED WITH THIS ITEM:
- Yes
- CITY/STATE/FEDERAL FUNDS:
- City/State
- TOTAL:
- $291,635.66
- BUDGETED AMOUNT:
- $291,635.66
- AVAILABLE AMOUNT TO TRANSFER:
- N/A
- ACCT NAME & GL#/REMAINING BALANCE BEFORE PURCHASE:
- 255-210-90015.219/CIPMerrill Ave Improvements Phase ll/$377,570.00
FISCAL IMPACT STATEMENT (IF THIS IS A BUDGET TRANSFER, YOU MUST ATTACH THE BUDGET ADJUSTMENT FORM):
Project will be funded by CDBG Contract #114-18 from the Arizona Department of Housing and City funds.