ITEM:
Presentation followed by discussion and possible directions to staff on any and all matters regarding the West Wastewater Treatment Plant Expansion Project. (Eulogio Vera, Public Works Director, and Mike Krebs, Vice President of PACE Advanced Water Engineering)
SUMMARY:
The City of San Luis continues to be one of the fastest-growing cities in the State of Arizona. It is critical that we continue to ensure that the city's wastewater treatment capability and capacity are adequate for both near- and long-term residential, industrial and commercial growth. The Public Works Department has contracted with PACE Advanced Water Engineering (an approved on-call engineering consultant for the City of San Luis) to assess both near- and long-term demands for wastewater treatment and to provide recommended improvements (both quantitative and qualitative) to the city's wastewater treatment capabilities.
Mr. Mike Krebs of PACE Advanced Water Engineering will be presenting to the Mayor and Council the findings of the assessment as well as the recommended infrastructure improvements to the city's wastewater treatment capabilities. This presentation will also touch on different wastewater treatment processes and provide a thorough comparison between these processes, including cost analysis of the upfront needed investment as well as the cost associated with operation and maintenance.
Mr. Mike Krebs of PACE Advanced Water Engineering will be presenting to the Mayor and Council the findings of the assessment as well as the recommended infrastructure improvements to the city's wastewater treatment capabilities. This presentation will also touch on different wastewater treatment processes and provide a thorough comparison between these processes, including cost analysis of the upfront needed investment as well as the cost associated with operation and maintenance.
RECOMMENDATION / SUGGESTED MOTION:
DISCUSSION AND POSSIBLE DIRECTIONS TO STAFF ONLY, NO ACTION ITEM.
Fiscal Impact
- IS THERE FISCAL IMPACT ASSOCIATED WITH THIS ITEM:
- Not at this time
- CITY/STATE/FEDERAL FUNDS:
- N/A
- TOTAL:
- N/A
- BUDGETED AMOUNT:
- N/A
- AVAILABLE AMOUNT TO TRANSFER:
- N/A
- ACCT NAME & GL#/REMAINING BALANCE BEFORE PURCHASE:
- N/A
FISCAL IMPACT STATEMENT (IF THIS IS A BUDGET TRANSFER, YOU MUST ATTACH THE BUDGET ADJUSTMENT FORM):
There is no fiscal impact associated with this item/presentation. There will be an impact associated with the future expansion of the west wastewater treatment plant, but that will be presented at a later Council session.