AGENDA ITEM REVIEW FORM
6.A.
Regular City Council Meeting
Meeting Date:
09/28/2016
Department Head:
Eulogio Vera
Submitted By:
Liliana Evangelista, Administrative Coordinator, Public Works Department
Action Requested:
Motion

ITEM:

Discussion and possible action on any and all matters regarding authorization to award a construction contract to LPC Construction, Inc. for the Juan Sanchez Boulevard Sewer Lift Station Project. (Eulogio Vera, Public Works Director)

SUMMARY:

The City of San Luis went out to formal bid pursuant to Title 34 of the Arizona Revised Statutes for the construction of a new sewer lift station and new sewer force main.  Six (6) bids were submitted ranging from $2,083,849.23 to $2,969,806.35 with the lowest being from LPC Construction, Inc.  Completion of this project will accomplish the diversion of sewer flows from the West Wastewater Treatment Plant to the East Wastewater Treatment Plant and releasing capacity at the West Wastewater Treatment Plant to allow more development in the San Luis valley.  Staff is recommending the awarding of a contract to LPC Construction, Inc. to construct the Juan Sanchez Boulevard Sewer Lift Station per project plans and specifications in the amount of $2,083,849.23.  Project will be funded by bond monies.

RECOMMENDATION / SUGGESTED MOTION:

I MOTION TO

Fiscal Impact

IS THERE FISCAL IMPACT ASSOCIATED WITH THIS ITEM:
Yes
CITY/STATE/FEDERAL FUNDS:
City
TOTAL:
$2,083,849.23
BUDGETED:
$3,533,000.00
AVAILABLE TO TRANSFER:
N/A
GL ACCT # & NAME/REMAINING BALANCE BEFORE PURCHASE:
310-311-90015.350 Capital Outlay-CIP Water System $3,533,000.00

FISCAL IMPACT STATEMENT (IF THIS IS A BUDGET TRANSFER, YOU MUST ATTACH THE BUDGET ADJUSTMENT FORM):

Bond funds will be used to pay for this project and impact fee fund will be used to pay back this project's expense to the bond fund.