AGENDA ITEM REVIEW FORM
7.E.
Regular City Council Meeting
Meeting Date:
09/13/2023
Department Head:
Eulogio Vera
Submitted By:
Jorge Perez, Assistant Director of Public Works, Public Works Department
Action Requested:
Motion

ITEM:

Discussion and possible action on any and all matters regarding budget transfer and payment ratification on the intersection improvements on County 22nd Street and Sidewinder Road.  (Jorge Perez, Assistant Director of Public Works)

SUMMARY:

On May 3, 2023, the City of San Luis awarded phase one of the County 22nd Street and Sidewinder Avenue Intersection Improvements Project to DPE Construction Inc., following a formal bidding process. The Department of Public Works had an original budget of $171,212.00 for Fiscal Year 2023 (inclusive of $28,790.00 engineering costs) and a proposed construction schedule that would extend to Fiscal Year 2024, budgeting completion of the project in such year.  Once the contractor was under contract, their project schedule was intended to complete the majority of the work during the summer and enable them to open up the roadway when school started up again.  Staff was in favor of their proposed schedule to reduce the impact on the school and residential traffic, but it did create a shortfall of funding in FY2023. 

The Departments of Finance and Public Works worked together and were able to find funding from Fiscal Year 2023 projects to pay for the portion of the work completed by the contractor before June 30, 2023.  Staff is seeking council approval to process a budget transfer as presented on the fiscal impact of this item and to ratify the payment for the portion of the work completed in Fiscal Year 2023, as initially presented for payment in FY 2024.

RECOMMENDATION / SUGGESTED MOTION:

I MOVE TO APPROVE A BUDGET TRANSFER AND RATIFY PAYMENT OF PURCHASE ORDER 2023-4230 FOR CONSTRUCTION SERVICES AT COUNTY 22ND STREET AND SIDEWINDER ROAD INTERSECTION IMPROVEMENTS PHASE 1 AS STATED IN THIS AGENDA ITEM.

Fiscal Impact

IS THERE FISCAL IMPACT ASSOCIATED WITH THIS ITEM:
Yes
CITY/STATE/FEDERAL FUNDS:
City
TOTAL:
$698,840.00
BUDGETED AMOUNT:
$144,226.00
AVAILABLE AMOUNT TO TRANSFER:
See Fiscal Impact Statement
ACCT NAME & GL#/REMAINING BALANCE BEFORE PURCHASE:
See Fiscal Impact Statement

FISCAL IMPACT STATEMENT (IF THIS IS A BUDGET TRANSFER, YOU MUST ATTACH THE BUDGET ADJUSTMENT FORM):

The total cost for this project is $698,840.00, we incurred $645,138.00 through June 30, 2023, and $ $52,901.31 have been carried over to FY 2024. We have budget allocated in FY 2024 to cover the pending costs of the project.

For FY 2023 we have budget available for this project $144,226.00, hence we have a shortfall of $500,912.00. (Costs incurred to date $645,138.00 minus budget available $144,226.00)

To have enough funds to cover the budget shortfall, staff is requesting council's approval to do a budget transfer to account 200-210-91000 in the amount of $500,912.00 from Fiscal Year 2023 projects as follows:

Communication Towers - Account 100-999-90015 - $200,000.00
Recreation Building Expansion - Account 100-999-90015 - $65,000.00
Design of Municipal Court - Account 100-999-90015 - $15,000.00
Fleet Shop - Account 100-999-90015 - $200,000.00

Staff is requesting authorization to utilize available funding within the same CIP account as follows:
Avenue F Widening Design - Account 200-210-90010 - $20,912.00