AGENDA ITEM REVIEW FORM |
6.D.
Regular City Council Meeting
- Meeting Date:
- 06/26/2024
- Department Head:
- Roula Encinas
- Submitted By:
- Roula Encinas, Acting Director of Finance, Finance Department
Action Requested:
Board of Adjustment
Motion
Motion
ITEM:
Discussion and possible action on any and all matters regarding the authorization to reallocate budget funds from approved projects on March 27, 2024, to the partial payment for the APS Utility Re-allocation on Cesar Chavez Boulevard. (Jenny Torres, Acting City Manager)
SUMMARY:
On March 27, 2024, the City Council approved the budget transfer from projects that were originally adopted during the budget processing in the fiscal year 2023-2024 ("FY2024") to projects that we would include in the budget for the fiscal year 2024-2025 ("FY2025"). These were projects that we were able to complete for FY2024 to alleviate the budget for FY2025. However, we have identified the following projects that will not be completed by the end of FY2024 or that have remaining balances after completion.
- AZ State Land Acquisition of 18 acres
- Downtown Drainage Land Acquisition
- City Hall East Wing Design
- 10th Avenue Design and Construction
- Cesar Chavez ROW Acquisition
- Cesar Chavez Utility Relocation (Wastewater)
RECOMMENDATION / SUGGESTED MOTION:
I MOVE TO APPROVE A BUDGET TRANSFER AS STATED IN THE FISCAL IMPACT STATEMENT FOR THE PARTIAL PAYMENT OF $900,040.00 TO APS FOR UTILITY LINE RELOCATION FOR THE CESAR CHAVEZ BOULEVARD IMPROVEMENT PROJECT.
Fiscal Impact
- IS THERE FISCAL IMPACT ASSOCIATED WITH THIS ITEM:
- Yes
- CITY/STATE/FEDERAL FUNDS:
- Yes
- TOTAL:
- $900,040.00
- BUDGETED AMOUNT:
- See Fiscal Impact Statement
- AVAILABLE AMOUNT TO TRANSFER:
- See Fiscal Impact Statement
- ACCT NAME & GL#/REMAINING BALANCE BEFORE PURCHASE:
- See Fiscal Impact Statement
FISCAL IMPACT STATEMENT (IF THIS IS A BUDGET TRANSFER, YOU MUST ATTACH THE BUDGET ADJUSTMENT FORM):
We are requesting the City Council's authorization for a budget transfer from the unspent budget for FY2024 projects to the partial payment for the APS Utility reallocation on Cesar Chavez Blvd as detailed below:
| Debit | Credit | |||
| Streets | 200-210-90010 | 900,040.00 | APS Utility Re-allocation on Cesar Chavez Blvd. | |
| Admin | 100-999-90015 | 300,000.00 | AZ State Land acquisition of 18 acres for City Hall expansion. | |
| Admin | 100-999-90015 | 73,000.00 | The Downtown Drainage Land Acquisition project will not be completed. | |
| Admin | 100-999-90015 | 10,000.00 | City Hall East Wing Design | |
| Streets | 200-210-90010 | 75,000.00 | 10th Avenue Design and Construction | |
| Streets | 200-210-90010 | 200,000.00 | Cesar Chavez ROW Acquisition | |
| Streets | 310-311-90015 | 242,040.00 | Cesar Chavez Utility Relocation | |
| 900,040.00 | 900,040.00 |