AGENDA ITEM REVIEW FORM |
7.B.
Special City Council Meeting
- Meeting Date:
- 11/10/2026
- Department Head:
- Jessica Potts
- Submitted By:
- Crystal Ochoa, Administrative Coordinator, Parks & Recreation Department
Action Requested:
Motion
ITEM:
Discussion and possible action on any and all matters regarding the award of a construction contract to DWD Construction for the Joe Orduno Park Tennis Courts Renovation Project. (Jessica Potts, Director of Parks and Recreation)
SUMMARY:
The Parks and Recreation Department is seeking Mayor and City Council approval to award a construction contract to DWD Construction for the Joe Orduño Park – Tennis Courts Renovation Project.
The Tennis Courts Renovation Project is located at Joe Orduño Park in San Luis, Arizona. The project consists of the renovation of two existing tennis courts. The improvements include, but are not limited to, removal of existing tennis net and net posts, repair of existing chain-link fencing and gates, replacement of damaged fencing components, removal of existing court surface coatings, repair of cracks and surface imperfections, application of new acrylic court surfacing and striping, repainting of existing court features, installation of new tennis net posts, hardware, and nets, and all associated work necessary to restore the courts to a safe, functional, and playable condition, extend their service life, and improve recreational facilities for the community.
The City of San Luis was awarded $100,000.00 in community beautification funding from Arizona Public Service (APS) as part of its 140th anniversary celebration to support the renovation of two existing tennis courts and other structures at Joe Orduño Park.
City staff conducted a formal bidding process for the Joe Orduño Park – Tennis Courts Renovation Project. The bid solicitation included three (3) alternative bid schedules: Schedule A (complete rehabilitation of two tennis courts), Schedule B (complete rehabilitation of one tennis court), and Schedule C (reduced-scope rehabilitation of two tennis courts). Bidders were required to submit pricing for all three alternative bid schedules, allowing the City to select the most appropriate option based on available funding.
One (1) bid was received and opened on October 26, 2026, from DWD Construction, with the following bid amounts: Alternative Bid Schedule A Complete Rehabilitation of Two Tennis Courts: $167,079.00. Alternative Bid Schedule B – Complete Rehabilitation of One Tennis Court: $87,267.44. Alternative Bid Schedule C – Reduced-Scope Rehabilitation of Two Tennis Courts: $160,800.00.
Following evaluation of the bid schedules, City staff determined that Alternative Bid Schedule A was the preferred option to proceed with the renovation of both tennis courts. Staff subsequently coordinated with DWD Construction to identify potential scope reductions resulting in Change Order No. 1.
Staff is requesting City Council approval to award the construction contract to DWD Construction for the Joe Orduño Park – Tennis Courts Renovation Project under Alternative Bid Schedule A in the amount of $167,079.00 and authorize staff to proceed with contract execution. Staff further recommends that the City Council approve Change Order No. 1, agreed upon with DWD Construction, which includes a reduction in project scope and cost, with certain elements of the work to be completed by City staff, resulting in a revised contract amount of $99,999.76.
This purchase falls under the bidding provisions of the City of San Luis Procurement Code Sections 3.05.030, 3.05.040, and 3.05.050.
As part of the strategy to complete both tennis courts with the available funding, City staff will be completing portions of the scope of work that was reduced from the contract. This will require additional funding for concrete, rebar, paint, decorative rock, and other materials that will be used for the completion of the tennis courts rehabilitation as well as the concession stand. Additional request will total $30,000.00.
The Tennis Courts Renovation Project is located at Joe Orduño Park in San Luis, Arizona. The project consists of the renovation of two existing tennis courts. The improvements include, but are not limited to, removal of existing tennis net and net posts, repair of existing chain-link fencing and gates, replacement of damaged fencing components, removal of existing court surface coatings, repair of cracks and surface imperfections, application of new acrylic court surfacing and striping, repainting of existing court features, installation of new tennis net posts, hardware, and nets, and all associated work necessary to restore the courts to a safe, functional, and playable condition, extend their service life, and improve recreational facilities for the community.
The City of San Luis was awarded $100,000.00 in community beautification funding from Arizona Public Service (APS) as part of its 140th anniversary celebration to support the renovation of two existing tennis courts and other structures at Joe Orduño Park.
City staff conducted a formal bidding process for the Joe Orduño Park – Tennis Courts Renovation Project. The bid solicitation included three (3) alternative bid schedules: Schedule A (complete rehabilitation of two tennis courts), Schedule B (complete rehabilitation of one tennis court), and Schedule C (reduced-scope rehabilitation of two tennis courts). Bidders were required to submit pricing for all three alternative bid schedules, allowing the City to select the most appropriate option based on available funding.
One (1) bid was received and opened on October 26, 2026, from DWD Construction, with the following bid amounts: Alternative Bid Schedule A Complete Rehabilitation of Two Tennis Courts: $167,079.00. Alternative Bid Schedule B – Complete Rehabilitation of One Tennis Court: $87,267.44. Alternative Bid Schedule C – Reduced-Scope Rehabilitation of Two Tennis Courts: $160,800.00.
Following evaluation of the bid schedules, City staff determined that Alternative Bid Schedule A was the preferred option to proceed with the renovation of both tennis courts. Staff subsequently coordinated with DWD Construction to identify potential scope reductions resulting in Change Order No. 1.
Staff is requesting City Council approval to award the construction contract to DWD Construction for the Joe Orduño Park – Tennis Courts Renovation Project under Alternative Bid Schedule A in the amount of $167,079.00 and authorize staff to proceed with contract execution. Staff further recommends that the City Council approve Change Order No. 1, agreed upon with DWD Construction, which includes a reduction in project scope and cost, with certain elements of the work to be completed by City staff, resulting in a revised contract amount of $99,999.76.
This purchase falls under the bidding provisions of the City of San Luis Procurement Code Sections 3.05.030, 3.05.040, and 3.05.050.
As part of the strategy to complete both tennis courts with the available funding, City staff will be completing portions of the scope of work that was reduced from the contract. This will require additional funding for concrete, rebar, paint, decorative rock, and other materials that will be used for the completion of the tennis courts rehabilitation as well as the concession stand. Additional request will total $30,000.00.
RECOMMENDATION / SUGGESTED MOTION:
I MOVE TO AWARD A CONTRACT TO DWD CONSTRUCTION FOR THE CONSTRUCTION OF THE CITY OF SAN LUIS JOE ORDUNO PARK TENNIS COURTS RENOVATION PROJECT IN THE AMOUNT OF $167,079.00, TO APPROVE CHANGE ORDER NO.1, AND TO APPROVE THE BUDGET TRANSFER IN THE FISCAL IMPACT STATEMENT, AS PRESENTED.
Fiscal Impact
- IS THERE FISCAL IMPACT ASSOCIATED WITH THIS ITEM:
- YES
- CITY/STATE/FEDERAL FUNDS:
- CITY
- TOTAL:
- $130,000.00
- BUDGETED AMOUNT:
- $100,000.00
- AVAILABLE AMOUNT TO TRANSFER:
- $30,000.00
- ACCT NAME & GL#/REMAINING BALANCE BEFORE PURCHASE:
- 255-144-90015 CAPITAL OUTLAY - CIP Balance $199,544.00
FISCAL IMPACT STATEMENT (IF THIS IS A BUDGET TRANSFER, YOU MUST ATTACH THE BUDGET ADJUSTMENT FORM):
In Fiscal Year 2026, the City of San Luis received a $100,000.00 grant from Arizona Public Service (APS) as part of the APS 140th Anniversary Beautification Project.
The APS grant will fully cover the contract amount for the reduced project scope. However, the City still needs additional materials, including concrete, rebar, paint, and decorative rock, to complete the remaining work in-house. These materials are estimated to cost approximately $30,000.
To cover these additional costs, City Council authorization is requested for a budget transfer of $30,000.00 from the Roof Repair at Cultural Center project to the Beautification of Joe Orduño Park project, as follows:
From:
The APS grant will fully cover the contract amount for the reduced project scope. However, the City still needs additional materials, including concrete, rebar, paint, and decorative rock, to complete the remaining work in-house. These materials are estimated to cost approximately $30,000.
To cover these additional costs, City Council authorization is requested for a budget transfer of $30,000.00 from the Roof Repair at Cultural Center project to the Beautification of Joe Orduño Park project, as follows:
From:
- GL Account: 100-999-89000 – Non-Departmental Non-Capital Project Account
- Project: Roof Repair at Cultural Center
- Project No.: 2027028
- GL Account: 255-144-90015 – Capital Outlay CIP
- Project: Beautification of Joe Orduño Park (FS1, Tennis Courts, Concession Stand)
- Project No.: 2027037
Attachments
- Bid Advertisement Yuma Sun
- Bid Advertisement Bajo El Sol
- Bid Documents
- Bid Tabulation
- Contract
- Change Order No. #1 DWD