AGENDA ITEM REVIEW FORM |
7.C.
Special City Council Meeting
- Meeting Date:
- 11/17/2026
- Department Head:
- Eulogio Vera
- Submitted By:
- Xochitl Lopez, Administrative Coordinator, Public Works Department
Action Requested:
Motion
ITEM:
Discussion and possible action on any and all matters regarding authorization to process a budget transfer to cover expenses associated with the Water Operations Building Expansion Project. (Jorge Perez, Assistant Director of Public Works)
SUMMARY:
The Public Works Department initiated the Water Operations Building Expansion Project toward the end of Fiscal Year 2026. During project planning and budgeting, staff anticipated the contractor could complete more construction work during FY26. Based on this anticipated schedule, the city budgeted $100,000 for the project in FY27, expecting the remaining project expenses to be incurred and encumbered during FY26.
However, delays in executing the construction contract and in commencing project activities affected the contractor's ability to advance the work as originally anticipated. As a result, the contractor completed only a portion of the work that staff had initially projected would be accomplished by the end of FY26. Consequently, the FY27 budget allocation was insufficient to cover the expenses associated with the remaining project work.
The resulting funding shortfall is $141,000.00. It is important to clarify that this request does not represent an increase in the overall project cost or project budget. Rather, it reflects the need to adjust the FY27 budget allocation to accommodate expenses originally anticipated to be incurred and encumbered in FY26 but carried forward into FY27 due to project schedule delays.
To address this funding requirement and ensure the continued progress of the project, staff is requesting City Council approval to authorize a budget transfer in the amount of $141,000.00 from Non-Capital Projects No. 2027-034 and 2027-035 to the Water Operations Building Expansion Project, as further detailed in the Fiscal Impact section of this agenda item.
However, delays in executing the construction contract and in commencing project activities affected the contractor's ability to advance the work as originally anticipated. As a result, the contractor completed only a portion of the work that staff had initially projected would be accomplished by the end of FY26. Consequently, the FY27 budget allocation was insufficient to cover the expenses associated with the remaining project work.
The resulting funding shortfall is $141,000.00. It is important to clarify that this request does not represent an increase in the overall project cost or project budget. Rather, it reflects the need to adjust the FY27 budget allocation to accommodate expenses originally anticipated to be incurred and encumbered in FY26 but carried forward into FY27 due to project schedule delays.
To address this funding requirement and ensure the continued progress of the project, staff is requesting City Council approval to authorize a budget transfer in the amount of $141,000.00 from Non-Capital Projects No. 2027-034 and 2027-035 to the Water Operations Building Expansion Project, as further detailed in the Fiscal Impact section of this agenda item.
RECOMMENDATION / SUGGESTED MOTION:
I MOVE TO APPROVE A BUDGET TRANSFER IN THE AMOUNT OF $141,000.00 FROM NON-CAPITAL PROJECTS TO THE WATER OPERATIONS BUILDING EXPANSION PROJECT AS PRESENTED.
Fiscal Impact
- IS THERE FISCAL IMPACT ASSOCIATED WITH THIS ITEM:
- Yes
- CITY/STATE/FEDERAL FUNDS:
- City
- TOTAL:
- $141,000.00
- BUDGETED AMOUNT:
- $100,000.00
- AVAILABLE AMOUNT TO TRANSFER:
- See fiscal impact statement
- ACCT NAME & GL#/REMAINING BALANCE BEFORE PURCHASE:
- See fiscal impact statement
FISCAL IMPACT STATEMENT (IF THIS IS A BUDGET TRANSFER, YOU MUST ATTACH THE BUDGET ADJUSTMENT FORM):
The construction contract for the Water Operations Building Expansion Project (Project No. 2026052) was awarded in the amount of $421,764.00. During FY26, the City paid $181,663.65 toward the contract, leaving a remaining contract balance of $240,100.35. The City had originally budgeted $100,000.00 for the project in FY27; however, due to delays in the initial execution of the construction contract and project commencement, the FY27 funding allocation is insufficient to cover the remaining project expenses. This results in a funding shortfall of approximately $140,100.00. To address this shortfall, staff is requesting authorization to transfer $140,100.00 from the following non-capital project accounts:
Transfer From:
- Water Storage Tank #6 (1MG Steel) Demo / Project No. 2027035 / Account No. 300-302-89000 / $100,000.00
- Water Valve Replacement Program / Project No. 2027034 / Account No. 300-302-89000 / $40,100.00
Transfer To:
- Water Operations Building Expansion / Project No. 2026052 / Account No. 300-302-90015 / $140,100.00
The requested transfer represents a reallocation of existing budget appropriations and does not increase the overall construction contract amount or project cost. The transfer will provide the additional FY27 budget authority necessary to cover the remaining contractual expenses associated with the project.
Transfer From:
- Water Storage Tank #6 (1MG Steel) Demo / Project No. 2027035 / Account No. 300-302-89000 / $100,000.00
- Water Valve Replacement Program / Project No. 2027034 / Account No. 300-302-89000 / $40,100.00
Transfer To:
- Water Operations Building Expansion / Project No. 2026052 / Account No. 300-302-90015 / $140,100.00
The requested transfer represents a reallocation of existing budget appropriations and does not increase the overall construction contract amount or project cost. The transfer will provide the additional FY27 budget authority necessary to cover the remaining contractual expenses associated with the project.