Title

Adopt Resolution #19-231 Authorizing Partial Payment #1 to Omann Contracting Companies, Inc. for Improvement Project #19-03, Wood Pond Hills and Chestnut Ridge Street Reconstruction.

Purpose/Background:

Resolution and Pay Estimate #1 attached.

Recommendation:

The Engineering Technician IV has inspected the completed work and recommends approving partial payment #1 to Omann Contracting Companies, Inc. for Improvement Project #19-03, Wood Pond Hills and Chestnut Ridge Street Reconstruction, in the amount of $252,037.83.

Action:

Motion to adopt Resolution #19-231 authorizing partial payment #1 to Omann Contracting Companies, Inc. for Improvement Project #19-03, Wood Pond Hills and Chestnut Ridge Street Reconstruction, in the amount of $252,037.83.

Attachments

Form Review

Inbox Reviewed By Date
Bruce Westby Bruce Westby 09/18/2019 12:53 PM
Bruce Westby Bruce Westby 09/18/2019 02:26 PM
Kurt Ulrich Kurt Ulrich 09/19/2019 03:34 PM
Form Started By:
Marsha Weidner
Started On:
09/17/2019 09:44 AM
Final Approval Date:
09/19/2019