Skip to main content

AgendaQuick™

View Agenda Item

6.2.
Public Works Committee
Meeting Date:
10/15/2019
By:
Bruce Westby, Engineering/Public Works

Title:

Staff Update on New Retainage Requirements for City Construction Contracts

Purpose/Background:

The following italicized text was copied from the League of Minnesota Cities website.
 
A new retainage law was enacted as part of the omnibus jobs, economic development, energy, and commerce finance bill (First Special Session Chapter 7) in article 9, sections 1 and 13. There were substantial changes this year, so cities should work with their city attorneys when entering into new contracts for public construction projects.
 
The new requirements, found in Minnesota Statutes, section 15.72, subdivision 2, and Minnesota Statutes, section 337.10, subdivision 4, are effective Aug. 1, and apply to agreements entered into on or after this date.
 
What retainage is
Retainage is a common practice in the private and public sectors, where a portion of the agreed-upon contract price is withheld until the construction work is complete to assure that the general contractor or subcontractor has satisfied their obligations.
 
Before the new law, 5% of the construction contract could be held for retainage from the general contractor. The general contractor, in turn, also was permitted to withhold 5% from its subcontractors.
 
Release of retainage
One of the most significant changes is when retainage must be released. Retainage must now be released no later than 60 days after “substantial completion” of a construction project, with some limited exceptions.
 
“Substantial completion” is defined consistently in Minnesota Statutes, section 541.051, subdivision 1(a). It is the date when construction is sufficiently completed so that the owner can occupy or use the improvement for the intended purpose. For streets, highways, and bridges, “substantial completion” is defined as the date when construction-related traffic devices and ongoing inspections are no longer required.
 
The general contractor must pay retainage to its subcontractors within 10 days after receiving retainage payment, unless there is a dispute about the work. The contractor must pay retainage to any subcontractor whose work is not involved in the dispute and must provide a written statement detailing the amount and reason for the withholding to the affected subcontractor.
 
Allowable withholding
After substantial completion, a city may still withhold (1) 250% of the cost to correct or complete work known at the time of substantial completion, and (2) the greater of $500 or 1 percent of the value of the contract for “final paperwork.”
 
Final paperwork is defined as documents required to fulfill contractual obligations including, but not limited to, operation manuals, payroll documents for projects subject to prevailing wage requirements, and the withholding exemption certificate required by Minnesota Statutes, section 270C.66 (IC 134 form).
 
If any payment is withheld for these reasons, a written statement must be promptly provided to the contractor, including the amount and basis of withholding. Withheld funds must be paid within 60 days after completion of the work or submission of final paperwork.
 
The new law also contains the following provisions:
  • Retainage reduction must be passed on to subcontractors. If the amount of retainage is reduced, the contractor must reduce retainage at the same rate for subcontractors.
  • Retainage cannot be held for warranty work. Withholding retainage for warranty work is prohibited. This provision does not waive any rights to warranty claims.
  • Certain requirements must be met before payment is made. The portion of a construction project funded with federal or state aid is only required to be paid when the federal or state aid has been received. Nothing in this section requires payment for a portion of a contract that is not complete or for which an invoice has not been submitted.
 
Cities should work with their city attorney and ensure that terms in their construction contracts are consistent with these changes in the law.


All parties to public construction contracts entered into after August 1, 2019 are subject to these new statutory requirements and limitations regarding the withholding and release of retainage, which is the portion of earned contract funds withheld by the owner from the contractor pending completion of the project. 
 
The most notable changes to the retainage laws that apply to City of Ramsey construction projects include:
  • The City must release all retainage within 60 days of substantial completion.
  • The Prime Contractor must release to its Subcontractors all remaining retainage as the Prime Contractor receives retainage from the City. Once the Prime Contractor has received retainage from the City, the Prime Contractor must pay retainage on undisputed work to its Subcontractors within 10 days. The Prime Contractor does not need to pay retainage on disputed work, but it must pay the undisputed portion and provide its Subcontractor with a written statement detailing the dispute.
  • The definition of “substantial completion” essentially remains the same, in other words when the work can be occupied and used for its intended purpose, but a provision was added for highway, street and bridge work to define substantial completion as when construction traffic control and inspections are no longer needed.
  • If punch list work remains after substantial completion, the City may continue to withhold up to 250% of the value of the punch list work. The City must provide the Prime Contractor with a written statement of the amount and reason for the withholding, and the Prime Contractor must provide a copy to any affected Subcontractor that requests it.
  • The City may withhold the lesser of 1% of the contract, or $500, until the final project paperwork (e.g., OEM manuals, prevailing wage documentation, etc.) is provided.
  • Withholding for warranty work is not permitted, but neither is any warranty claim waived.
 
The new law does not require payment for work yet to be completed or for which no invoice has been submitted, and the City does not need to pay for those portions of the work funded with federal or state aid until those funds are received.
 
In summary, though the new laws mean that Prime Contractors and their Subcontractors may not have to wait as long for their retainages to be paid, there is an increased risk of the premature release of retainages being held to ensure compliance and completion of work, which may increase the risk to the City.

Timeframe:

Staff estimates 5 minutes will be needed to present this case and address questions.

Observations/Alternatives:

Staff is working with the City Attorney to ensure the City’s construction contracts are consistent with and reflect these changes in the law.

Funding Source:

NA

Recommendation:

NA

Action:

No action required.  This is an informational item only.

Attachments

Form Review

Inbox Reviewed By Date
Grant Riemer MaryJo Warner 10/10/2019 03:41 PM
Kurt Ulrich Kathy Schmitz 10/10/2019 04:11 PM
Form Started By:
Bruce Westby
Started On:
10/10/2019 10:14 AM
Final Approval Date:
10/10/2019