5.3.
Public Works Committee
Meeting Date:
08/18/2020
By:
Bruce Westby, Engineering/Public Works

Title:

Consider Recommendation to City Council Authorizing Requests for Quotes for 9591 Inverness Lane Drainage Improvements, Improvement Project 20-08

Purpose/Background:

Purpose:
The purpose of this case is to consider a recommendation to City Council authorizing Requests for Quotes for 9591 Inverness Lane Drainage Improvements, Improvement Project 20-08.  

Background:
In December of 2015, the property owner at 9591 Inverness Lane first contacted Staff to inform us of some drainage concerns regarding the operation of the drainage ditch east of Jarvis Street on both sides of Inverness Lane, which has just been improved that summer as part of the Jarvis Street Reconstruction project.  Ramsey Staff met with Elk River Staff, who led this street reconstruction project, and with Staff from Bolton & Menk, who designed who designed and inspected the project. The outcome of that conversation was that some grading modifications were made as part of the project punch list work.  Then on June 12, 2016, the property owner at 9591 Inverness Lane reached out again to let us know the ditch appeared to be flowing well and that his concerns had been addressed.
 
In early 2019, the property owner contacted Staff again to report that the swale traversing their back yard, which conveys stormwater runoff from several properties upstream, was full of water and was roughly 10 feet from the back of their house and encroaching under the rear edge of their deck.  The property owner said it had never been this full of water before.  That spring, Staff began working on plans to improve drainage in the ditch east of Jarvis Street, including collecting survey shots and investigating options for improving drainage in the ditch east of Jarvis Street to prevent water from backing up into the back yard of this property.
 
During late winter and early spring, snow and ice in the ditch prevents runoff from flowing properly, causing stormwater runoff to back up into the swale in the back yard of 9591 Inverness Lane.  Staff confirmed the ditch to the south of Inverness does not have proper slope for drainage. Staff originally looked at re-grading the ditch east of Jarvis Street to the existing pond one lot south of Inverness Lane. Due to existing private utilities, poles, impacts to existing mature trees, and to avoid steep ditch side slopes, Staff determined piping the runoff through this stretch to be the more feasible approach.
 
This project proposes to remove the existing bituminous flumes and culvert under Inverness Lane and replace them with storm sewer pipe and catch basins.  Storm sewer pipe will then be extended in City right-of-way east of Jarvis Street to the south edge of the property south of Inverness Lane, where it will tie into the existing ditch that routes runoff to an existing stormwater pond. Fill will be placed over the storm sewer pipe, and a shallow swale will be graded above the pipe to route runoff from the street and adjacent properties to the existing ditch and stormwater pond.  Attached is a plan sheet showing the proposed improvements, which was reviewed with the property owner.
 
This drainage improvement project is proposed to be completed this fall.  Based on the current bid environment Staff anticipates receiving good quotes.   

Timeframe:

Staff estimates approximately 15 minutes will be required for presentation and discussion of this case. 

Observations/Alternatives:

Observations:
Staff plans to request City Council approval of plans and specifications and authorization to request quotes on August 25th.  Construction is proposed to be completed by October 23, 2020, with final payment issued during the summer of 2021 after turf has been established and approved.   
 
Alternatives:
Alternative #1: Motion to recommend City Council authorization for Requests for Quotes for 9591 Inverness Lane Drainage Improvements, Improvement Project 20-08. 

Alternative #2: Motion of other. 

Funding Source:

Estimated construction costs for this project total $58,000 and are based on final plans and specifications as prepared by City Staff.  Construction staking is proposed to be provided by a consultant at an estimated cost of $5,500.  A proposal for construction staking will be presented to the City Council at the time Staff requests approval of a construction contract to the contractor submitting the lowest quote.
 
All project costs are proposed to be split evenly between the Stormwater Management and Stormwater Utility Funds.  

Recommendation:

Staff recommends alternative #1. 

Action:

Motion to recommend City Council authorize Requests for Quotes for 9591 Inverness Lane Drainage Improvements, Improvement Project 20-08. 

Attachments

Form Review

Inbox Reviewed By Date
Brian Hagen Tim Gladhill 08/13/2020 01:50 PM
Grant Riemer Grant Riemer 08/13/2020 02:39 PM
Kurt Ulrich MaryJo Warner 08/13/2020 02:52 PM
Form Started By:
Bruce Westby
Started On:
08/12/2020 11:05 AM
Final Approval Date:
08/13/2020