5.33.
CC Regular Session
- Meeting Date:
- 12/14/2021
- By:
- Katie Schmidt, Administrative Services
Information
Title
Adopt Resolution #21-357 Authorizing Partial Payment #15 to RJM Construction for Improvement Project 20-07 New Public Works Facility
Purpose/Background:
Resolution and Pay Estimate #15 attached.
Observations/Alternatives:
Checks are made payable and addressed to contractors, payments will be sent to RJM Construction, LLC for disbursement as listed in the attached Resolution #21-357.
Funding Source:
Funding for this this item was budgeted as part of the public works building project.
Recommendation:
The Public Works Superintendent has inspected the completed work and recommends approving partial payment #15 in the amount of $609,565.25 to RJM Construction for Improvement Project #20-07, New Public Works Facility.
Action:
Motion to adopt Resolution #21-357 authorizing partial payment #15 to RJM Construction for Improvement Project #20-07, New Public Works Facility.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Grant Riemer | MaryJo Warner | 12/09/2021 08:29 AM |
| Mary Jo Warner | MaryJo Warner | 12/09/2021 11:45 AM |
| Grant Riemer | Grant Riemer | 12/09/2021 12:33 PM |
| Kurt Ulrich | Kurt Ulrich | 12/09/2021 01:28 PM |
- Form Started By:
- Katie Schmidt
- Started On:
- 12/07/2021 03:22 PM
- Final Approval Date:
- 12/09/2021