5.5.
Public Works Committee
- Meeting Date:
- 03/15/2022
- By:
- Bruce Westby, Engineering/Public Works
Title:
Consider Recommending City Council Approval to Advance Construction of 2022 - 2031 Capital Improvement Program Projects #19-STR-004 and #21-PARK-002 from 2024 to 2023.
Purpose/Background:
Purpose:
To consider recommending City Council approval to advance the reconstruction of 161st Avenue between Armstrong Boulevard and Variolite Street as identified in the 2022 - 2031 Capital Improvement Program from 2024 to 2023.
Background:
As discussed at the March 8th City Council meeting, PACT Charter School is proposing to construct a new school to serve grades 6-12 on roughly 18-acres of the 33-acre site owned by the Church of Saint Katharine Drexel at 7633 161st Ave NW. Per their current project schedule, PACT Charter plans to open the new school in the fall of 2023 meaning the new school will be under construction during the fall of 2022 through the summer of 2023. Attached are copies of PACT Charter school's proposed sketch plan, project narrative, ALTA survey, and preliminary plat for reference.
The 2022 - 2031 Capital Improvement Program includes the following two projects along the segment of 161st Avenue between Armstrong Boulevard and Variolite Street.
Considering PACT Charter schools proposal, Staff recommends advancing construction of both projects from 2024 to 2023 to prevent the need to reconstruct 161st Avenue after PACT Charter school opens its new campus, which will result in increased traffic volumes making it more difficult to reconstruct under traffic and possibly increasing bid prices.
To consider recommending City Council approval to advance the reconstruction of 161st Avenue between Armstrong Boulevard and Variolite Street as identified in the 2022 - 2031 Capital Improvement Program from 2024 to 2023.
Background:
As discussed at the March 8th City Council meeting, PACT Charter School is proposing to construct a new school to serve grades 6-12 on roughly 18-acres of the 33-acre site owned by the Church of Saint Katharine Drexel at 7633 161st Ave NW. Per their current project schedule, PACT Charter plans to open the new school in the fall of 2023 meaning the new school will be under construction during the fall of 2022 through the summer of 2023. Attached are copies of PACT Charter school's proposed sketch plan, project narrative, ALTA survey, and preliminary plat for reference.
The 2022 - 2031 Capital Improvement Program includes the following two projects along the segment of 161st Avenue between Armstrong Boulevard and Variolite Street.
- Project #19-STR-004, Reconstruction of 161st Avenue, involves reconstructing 161st Avenue between Armstrong Boulevard and Variolite Street.
- Project #21-PARK-002, Central Park Main Parking Lot Reconstruction, involves reconstructing the 35+ year-old bituminous pavement in the main parking area.
Considering PACT Charter schools proposal, Staff recommends advancing construction of both projects from 2024 to 2023 to prevent the need to reconstruct 161st Avenue after PACT Charter school opens its new campus, which will result in increased traffic volumes making it more difficult to reconstruct under traffic and possibly increasing bid prices.
Timeframe:
Staff anticipates 10 minutes will be needed to present this case and respond to questions.
Observations/Alternatives:
Alternative #1 – Motion to recommend City Council approval to advance construction of 2022 - 2031 Capital Improvement Program projects #19-STR-004 and #21-PARK-002 from 2024 to 2023.
Alternative #2 – Motion of other.
Alternative #2 – Motion of other.
Funding Source:
Funding sources for each project are identified within the respective attached CIP sheets. The required funding for each project will be available in 2023.
Recommendation:
Staff recommends approving alternative #1.
Action:
Motion to recommend City Council approval to advance construction of 2022 - 2031 Capital Improvement Program projects #19-STR-004 and #21-PARK-002 from 2024 to 2023.
Attachments
- 19-STR-004 CIP Sheet
- 21-PARK-002 CIP Sheet
- PACT Sketch Plan
- PACT Project Narrative
- PACT ALTA Survey
- PACT Prelim Plat
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Grant Riemer | MaryJo Warner | 03/10/2022 02:17 PM |
| Kurt Ulrich | Kurt Ulrich | 03/10/2022 03:33 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 03/08/2022 01:06 PM
- Final Approval Date:
- 03/10/2022