Progress Update on Water Treatment Plant
Purpose/Background:
Purpose:
The purpose of this case is to update the committee on the progress of the design phase for the Water Treatment Plant Project #21-09 and present the most up-to-date project timeline and engineer's cost estimate.
The purpose of this case is to update the committee on the progress of the design phase for the Water Treatment Plant Project #21-09 and present the most up-to-date project timeline and engineer's cost estimate.
Timeframe:
20 Minutes
Observations/Alternatives:
Steve Nelson and Abbie Browman from AE2S will be on hand to present a brief Power Point presentation illustating design features of the plant and review current project timelines and cost estimates. We are currently at 75% plan completion.
Funding Source:
Water Utility Fund
Recommendation:
Informational Only
Action:
Based on committe discussion
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Brian Hagen | Brian Hagen | 05/12/2022 01:05 PM |
- Form Started By:
- Grant Riemer
- Started On:
- 05/11/2022 08:26 AM
- Final Approval Date:
- 05/12/2022