6.2.
Public Works Committee
- Meeting Date:
- 08/22/2022
- By:
- Bruce Westby, Engineering/Public Works
Title:
Receive Updates on Improvement Projects, Studies and Items of Interest
Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.
City Improvement Projects
City of Anoka Improvement Projects
Anoka County Improvement Projects
MnDOT Improvement Projects
Studies & Items of Interest
City Improvement Projects
- 161st Avenue Reconstruction (IP #23-01)
- Staff will provide a brief update of August 23rd City Council agenda case
- Staff proposes to construct Central Park parking lot improvements separately
- 167th Avenue Reconstruction (IP #23-04)
- Staff will provide a brief update of August 23rd City Council agenda case
- Sunwood Drive & Waco Street Reconstructions (IP #22-01)
- Construction in progress
- Autumn Heights Street Reconstructions (IP #22-02)
- Preconstruction meeting will be held soon
- 2022 Neighborhood Street Overlay Improvements (IP #22-04)
- Construction in progress
- Riverdale Drive Trunk Utility Improvements (IP #22-05)
- Construction of sanitary sewer lift station nearing completion
- Wood Pond Hills 2nd, 3rd, 4th, 5th Street Reconstructions (IP #22-06)
- Construction in progress
- 2022 MSA Pavement Striping Improvements (IP #22-13)
- Council to consider awarding a construction contract August 23rd
- 15410 Argon Street Drainage Improvements (IP #22-14)
- See separate case
- Highway 47 Sound Wall north of Xkimo Street (IP #22-17)
- PWC received request from Xkimo Court residents October 19, 2021
- PWC last reviewed costs and options May 17th
- PWC to consider updated costs and options September 20th
- WTP Trunk Watermain Improvements (#21-08)
- First bids rejected January 25, 2022
- Plans are being revised to minimize project costs without sacrificing quality, and to include WTP commissioning improvements (well-house valves, etc.).
- Council to consider revised contract with SEH, Inc. September 27th
- Council to consider re-bidding revised plans September/October
- Project completion proposed March 2024
- Centralized Water Treatment Plant (#21-09)
- AE2S preparing plans, handling construction administration
- 100-percent plans under review by Staff
- Council to consider approving plans and authorizing bids September 27th
- Project completion proposed May 2024 (2-year construction schedule)
- Ramsey Gateway Highway 10 Improvements (IP #20-11)
- Final design and property acquisitions in progress
- Bolton & Menk preparing plans and specifications
- 60-percent plans under review by Staff
- Construction anticipated Fall 2023 through early 2026 (2024/25 majority)
- Riverdale Drive Extension – Llama Street to Bowers Drive (IP #20-05)
- Preconstruction meeting held August 17th
- Substantial completion proposed September 30th
- Final completion proposed October 31st
- Wetland 114P Outlet Control Improvements (#19-07)
- Requested by Minnesota DNR
- Staff is preparing plans, including boardwalk reconstruction
- Construction proposed for winter 2022/2023
City of Anoka Improvement Projects
- Highway 47 Corridor Improvements
- Construction proposed for 2025
- Anoka webpage https://clients.bolton-menk.com/anokahwy47/
Anoka County Improvement Projects
- Roundabout at Armstrong Boulevard/CSAH 83 and Alpine Drive (IP #23-03)
- Anoka County received $1.35M in HSIP funds (est. project cost $1.5M)
- Council approved JPA May 24th with City cost share = $28,667.64
- Construction proposed for 2023, pending final City & County approvals
MnDOT Improvement Projects
- Anoka Solution Highway 10 Improvements
- Construction in progress
- Final completion proposed for Spring 2024
- Anoka webpage https://clients.bolton-menk.com/hwy10/
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy10-anoka/
- US 10 / 169 & Ferry Street / TH 47 Interchange
- Construction in progress with completion proposed in Spring 2024
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy10-anoka/
- Ferry Street / Trunk Highway 47 Grade Separation @ BNSF Rail Crossing
- Preliminary design suspended to explore s-curve realignment
- $45M in bonds authorized October 2020
- Construction proposed for 2024 or later
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy47rr-anoka/
- Rum River Bridge Replacement
- Construction in progress with completion proposed in Spring 2024
- Proposing three lanes each direction between Highway 47 and 7th Street
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy10-anoka/
Studies & Items of Interest
- 5805 148th Lane NW
- No updates. Property owners are content as is.
- CSAH 5/Nowthen Boulevard Corridor Study
- Final report will be reviewed with PWC in Fall 2022
- Elk River Highway 10 Corridor Study
- Study website https://www.highway10corridorstudy.com/
- Final report will be reviewed with PWC in Fall 2022
Timeframe:
Staff estimates up to 30 minutes will be needed for updates and discussion.
Observations/Alternatives:
NA
Funding Source:
NA
Recommendation:
Staff does not have recommendations to offer on these topics at this time.
Action:
No formal action required. For Committee review and discussion purposes only.
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Brian Hagen | Brian Hagen | 08/18/2022 03:28 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 08/18/2022 11:16 AM
- Final Approval Date:
- 08/18/2022