Title:
Receive Updates on Improvement Projects, Studies and Items of Interest
Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.
City Improvement Projects
City of Anoka Improvement Projects
Anoka County Improvement Projects
MnDOT Improvement Projects
Studies & Items of Interest
City Improvement Projects
- 161st Avenue Reconstruction (IP #23-01)
- Staff is preparing plans and specifications
- Staff is coordinating design with PACT Charter school
- Staff applied for trail grant funding per Council approval
- 2023 construction proposed
- 167th Avenue Reconstruction (IP #23-04)
- Staff proposes to use Bolton & Menk to prepare plans and specs and evaluate regional trail alignment and pedestrian crossings
- Staff applied for trail grant funding per Council approval
- 2023 construction proposed
- Sunwood Drive & Waco Street Reconstructions (IP #22-01)
- Construction complete è punch list mode
- Autumn Heights Street Reconstructions (IP #22-02)
- Construction complete è punch list mode
- 2022 Neighborhood Street Overlay Improvements (IP #22-04)
- Construction complete è punch list mode
- Riverdale Drive Trunk Utility Improvements (IP #22-05)
- Construction complete è punch list mode
- Wood Pond Hills 2nd, 3rd, 4th, 5th Street Reconstructions (IP #22-06)
- Construction complete è punch list mode
- 15410 Argon Street Drainage Improvements (IP #22-14)
- Construction in progress
- Highway 47 Sound Wall north of Xkimo Street (IP #22-17)
- See separate case on agenda
- WTP Trunk Watermain Improvements (#21-08)
- Plans are being revised to minimize project costs and include WTP commissioning improvements (well-house valves, etc.)
- City Council will consider authorizing bids when plans are complete
- Centralized Water Treatment Plant (#21-09)
- New AE2S Project Manager is reviewing plans to ensure cost-effectiveness of design and materials
- Cost estimate will be updated after plans are complete
- City Council will consider authorizing bids on January 10, 2023
- Ramsey Gateway Highway 10 Improvements (IP #20-11)
- Final design nearly complete
- Property/easement acquisitions in progress
- Construction anticipated 2023 through early 2026 (2024 - 2025 majority)
- Riverdale Drive east of SLB & temp US 10 widening Spring/Summer 2023
- Riverdale Drive Extension – Llama Street to Bowers Drive (IP #20-05)
- Construction complete è punch list mode
- Wetland 114P Outlet Control Improvements (#19-07)
- See separate case on agenda
City of Anoka Improvement Projects
- Highway 47 Corridor Improvements
- Construction proposed for 2025
- Anoka webpage https://clients.bolton-menk.com/anokahwy47/
Anoka County Improvement Projects
- Roundabout at Armstrong Boulevard/CSAH 83 and Alpine Drive (IP #23-03)
- Anoka County received $1.35M in HSIP funds (est. project cost $1.5M)
- JPA includes City cost share of $28,667.64
- Construction proposed for 2023 pending final City & County approvals
MnDOT Improvement Projects
- Anoka Solution Highway 10 Improvements
- Final completion Spring 2024
- 2-lanes open for winter
- Anoka webpage https://clients.bolton-menk.com/hwy10/
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy10-anoka/
- US 10 / 169 & Ferry Street / TH 47 Interchange
- Final completion Spring 2024
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy10-anoka/
- Ferry Street / Trunk Highway 47 Grade Separation @ BNSF Rail Crossing
- Preliminary design suspended to explore s-curve realignment
- $45M in bonds authorized October 2020
- Construction proposed for 2024 or later
- Public Open House November 14th (MnDOT mailing attached)
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy47rr-anoka/
- Rum River Bridge Replacement
- Final completion Spring 2024
- Three lanes each direction
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy10-anoka/
Studies & Items of Interest
- Sunfish Lake Sedimentation Basin Improvements
- Property owner still interested in pursuing their request
- Staff will delineate rear property line this Fall
- Staff anticipates presenting an update in January
- CSAH 5 / Nowthen Boulevard Corridor Study
- Staff will present the final report when available
- Elk River Highway 10 Corridor Study
- Staff will present the final report when available
- Study website https://www.highway10corridorstudy.com/
Timeframe:
Staff estimates up to 15 minutes will be needed for updates and discussion.
Observations/Alternatives:
NA
Funding Source:
NA
Recommendation:
NA
Action:
No formal action required. For Committee review and discussion purposes only.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Brian Hagen | Brian Hagen | 11/10/2022 10:46 AM |
- Form Started By:
- Bruce Westby
- Started On:
- 11/09/2022 11:39 AM
- Final Approval Date:
- 11/10/2022