Bruce Westby, Engineering/Public Works

Title:

Receive Updates on Improvement Projects, Studies and Items of Interest

Purpose/Background:

The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.

City Improvement Projects
  • 161st Avenue Reconstruction (IP #23-01)
    • Staff is preparing plans and specifications
    • Staff is coordinating design with PACT Charter school
    • Staff applied for ATIP trail grant funding per Council approval
    • 2023 construction proposed
  • Central Park Parking Lot Reconstruction (IP #23-02)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • 167th Avenue Reconstruction (IP #23-04)
    • Bolton & Menk is preparing plans and specs per Council approval
    • Staff applied for ATIP trail grant funding per Council approval
    • 2023 construction proposed
  • Barthels Rum River Acres 2nd Reconstruction (IP #23-05)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • 2023 MSA Pavement Overlay Improvements (IP #23-06)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • 2023 Neighborhood Pavement Overlay Improvements (IP #23-07)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • 2023 Crack Seal Improvements (IP #23-08)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • 2023 Pavement Rejuvenator Improvements (IP #23-09)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • Whispering Pines Estates Plat 3 Reconstructions (IP #23-10)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • Trott Brook Crossing Sanitary Sewer Lift Station Improvements (IP #23-11)
    • Bolton and Menk is preparing plans and specifications per Council approval
    • 2023 construction proposed
  • HY-10 Ramsey Improvements (IP #23-12)
    • Bolton and Menk is preparing plans and specifications per Council approval
    • 2023 construction proposed to support ARAA sports dome project
  • Autumn Heights Street Reconstructions (IP #22-02)
    • Construction complete è punch list mode
  • Riverdale Drive Trunk Utility Improvements (IP #22-05)
    • Construction complete è punch list mode
  • Highway 47 Sound Wall north of Xkimo Street (IP #22-17)
    • City Council will consider authorizing bids soon (March/April)
  • WTP Trunk Watermain Improvements (#21-08)
    • Plans are being revised to minimize project costs and include WTP commissioning improvements (well-house valves, etc.)
    • City Council will consider authorizing bids when plans are complete
  • Centralized Water Treatment Plant (#21-09)
    • Bid opening March 9th @ 1 PM
    • City Council to consider accepting bids and awarding contract March 28th  
  • Ramsey Gateway Highway 10 Improvements (IP #20-11)
    • Final design nearly complete
    • Property/easement acquisitions nearly complete
    • Construction anticipated mid 2023 through early 2026 (2024 - 2025 majority)
    • Riverdale Drive east of SLB & temp US 10 widening mid 2023
  • Riverdale Drive Extension – Llama Street to Bowers Drive (IP #20-05)
    • Construction substantially complete è Hwy 10 improvements still needed
  • Wetland 114P Outlet Control Improvements (#19-07)
    • Executing contract
    • Awaiting DNR Permit
 
City of Anoka Improvement Projects  
Anoka County Improvement Projects
  • Roundabout at Armstrong Boulevard/CSAH 83 and Alpine Drive (IP #23-03)
    • Anoka County received $1.35M in HSIP funds (est. project cost $1.5M)
    • JPA includes City cost share of $28,667.64
    • Bids opened February 13th (results as yet unknown)
 
MnDOT Improvement Projects  
Studies & Items of Interest
  • Sunfish Lake Sedimentation Basin Improvements
    • Property owner interested in pursuing request to fill swale and grade basin
    • Staff delineated rear property line last Fall and notified property owner
    • Staff contacted property owner again in February by email and letter
  • CSAH 5 / Nowthen Boulevard Corridor Study
    • Final report will be presented February 21st
  • Elk River Highway 10 Corridor Study

Timeframe:

Staff estimates up to 15 minutes will be needed for updates and discussion.  

Observations/Alternatives:

N/A

Funding Source:

N/A

Recommendation:

N/A

Action:

No formal action required.  For Committee review and discussion purposes only.  

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Brian Hagen Brian Hagen 02/16/2023 03:09 PM
Form Started By:
Bruce Westby
Started On:
02/09/2023 01:52 PM
Final Approval Date:
02/16/2023