5.4.
Public Works Committee
Meeting Date:
04/18/2023
Submitted For:
Joe Feriancek
By:
Joe Feriancek, Engineering/Public Works

Title:

Consider Recommending City Council Approval of adding streets within Rivenwick 3rd and Rivenwick Village subdivisions to 2023 MSA Pavement Overlay Improvements, Improvement Project #23-06

Purpose/Background:

Purpose:
The purpose of this case is to consider recommending City Council approval of adding streets within Rivenwick 3rd and Rivenwick Village subdivisions to 2023 MSA Pavement Overlay Improvements, Improvement Project #23-06.
 
Background:
On December 13, 2022, the Ramsey City Council ordered the City Engineer to prepare plans and specifications for Improvement Project #23-06, 2023 MSA Pavement Overlay Improvements. This project proposes to mill and overlay 0.61 miles of Riverdale Drive between Ramsey Boulevard and Feldspar Street.
 
In March of 2023, Staff received concerns from residents about the condition of 139th Lane and Jaspar Street, a loop road off of Riverdale Drive west of Feldspar Street. Staff followed up on the concerns with a site visit and noted significant pavement stripping is occurring on the streets within the Rivenwick 3rd and Rivenwick Village subdivisions. A street segment summary and pictures of the pavement conditions are attached to this case for reference.
 
The current 2023 through 2032 10-year Capital Improvement Program (CIP) proposes pavement mill and overlay improvement for Rivenwick 3rd and Rivenwick Village in 2025.  Staff proposes to move the improvements up to 2023 and to include as part of the 2023 MSA Pavement Overlay Improvements for the following reasons:
  • Pavement stripping exposes the bituminous pavement to further damage. If not treated, the pavement conditions may rapidly decay to the point where a mill and overlay is no longer the suitable treatment.
  • By including this as a 2023 improvement, it frees up resources to patch other areas of the City during 2023 and likely 2024. Typically, once pavement stripping occurs, it will migrate to adjacent pavement.
  • Because the subdivisions are immediately adjacent to Riverdale Drive, already proposed to be milled and overlaid, additional mobilization costs are avoided.
  • The 2023 Neighborhood Pavement Overlay Improvements is already out for bid, with bids to be opened April 21, 2023. Adding these subdivisions to the 2023 MSA Pavement Overlay Improvements project avoids delays in starting the 2023 Neighborhood Overlay Improvements. The 2023 Neighborhood Overlays are proposed to be substantially complete by June 30, 2023.
  • The CIP proposes funding these improvements from Pavement Management Funds in 2025. The same funds would be used, just moved up to 2023.
 
2023 MSA Pavement Overlay Improvements Proposed Schedule:
  • May 23, 2023                      City Council approve plans & authorize advertisement for bids
  • May 26; June 2, 2023          Advertisement for bids
  • June 19, 2023                     Bid opening
  • June 27, 2023                     City Council award contract to lowest responsible bidder
  • July 10, 2023                       Approximate start of construction
  • Sep 1, 2023                         Substantial Completion

Timeframe:

Staff estimates 15 minutes will be needed to present this case and respond to questions.

Observations/Alternatives:

Observations:
Rivenwick Village includes two existing pedestrian ramps not up to current ADA standards which require additional topographic survey. Staff proposes to complete the additional topographic survey required to reconstruct the pedestrian ramps to current ADA standards in-house.
 
Staff feels combining these subdivisions with the 2023 MSA Improvements will have an overall cost savings for the City by avoiding potentially 2-3 seasons of pothole patching maintenance. At the same time, this allows maintenance crews to focus their efforts in different neighborhoods.
 
Alternatives:
Alternative #1 – Motion to recommend City Council approval of adding streets within Rivenwick 3rd and Rivenwick Village subdivisions to 2023 MSA Pavement Overlay Improvements, Improvement Project #23-06.
 
Alternative #2 – Motion of other.

Funding Source:

Funding for the improvements within Riverdale Drive right of way is proposed to come from a combination of Municipal State Aid funds and Storm Sewer Utility Funds. Improvements within the Rivenwick 3rd and Rivenwick Village subdivisions is proposed to come from a combination of Pavement Management Funds and Storm Sewer Utility Funds.
 
CIP Level Estimates:
Subdivision MSA Funds PM Funds Storm Sewer Funds Total
Riverdale Drive (Ramsey Blvd / Feldspar St) $190,625   $19,063 $209,688
Rivenwick 3rd   $61,200 $6,120 $67,320
Rivenwick Village   $102,000 $10,200 $112,200
Funding Totals $190,625 $163,200 $35,383 $389,208

Recommendation:

Staff recommends alternative #1.

Action:

Motion to recommend City Council approval of adding streets within Rivenwick 3rd and Rivenwick Village subdivisions to 2023 MSA Pavement Overlay Improvements, Improvement Project #23-06.

Attachments

Form Review

Inbox Reviewed By Date
Bruce Westby Bruce Westby 04/13/2023 01:46 PM
Bruce Westby Bruce Westby 04/13/2023 02:02 PM
Brian Hagen Brian Hagen 04/13/2023 04:20 PM
Form Started By:
Joe Feriancek
Started On:
04/06/2023 08:17 AM
Final Approval Date:
04/13/2023