Adopt Resolution #23-210 Authorizing Partial Payment #1 to Magney Construction, Inc. for Improvement Project #21-09, Centralized Water Treatment Plant
Purpose/Background:
Purpose:
Adopt Resolution #23-210 Authorizing Partial Payment #1 to Magney Construction, Inc. for Improvement Project #21-09, Centralized Water Treatment Plant.
Background:
Pay Application #1 and supporting Resolution are attached.
Adopt Resolution #23-210 Authorizing Partial Payment #1 to Magney Construction, Inc. for Improvement Project #21-09, Centralized Water Treatment Plant.
Background:
Pay Application #1 and supporting Resolution are attached.
Notification:
N/A
Observations/Alternatives:
N/A
Funding Source:
Funding will be paid from sewer and water enterprise funds.
Recommendation:
The Resident Project Representative from Advanced Engineering and Environmental Services (AE2S) has inspected the completed work and recommends approving partial payment #1 in the amount of $907,341.20 to Magney Construction, Inc. for Improvement Project #21-09, Centralized Water Treatment Plant.
Action:
Adopt Resolution #23-211 authorizing partial payment #1 to Magney Construction, Inc. for Improvement Project #21-09, Centralized Water Treatment Plant.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Brian Hagen | Brian Hagen | 09/07/2023 01:51 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 09/05/2023 08:13 AM
- Final Approval Date:
- 09/07/2023