5.5.
| CC Regular Session |
| Meeting Date: | 11/28/2023 |
| Primary Strategic Plan Initiative: | {ud_pd7} |
Information
Title
Adopt Resolution #23-224, Approving Final Payment to A & B Construction LTD, for IP #22-10, Public Works Salt Shed.
Purpose/Background:
Resolution and Pay Request Attached.
Observations/Alternatives:
Issuing final payment will be contingent on receipt of the following items from contractor, A & B Construction LTD.
1. IC-134 (Contractor's Withholding Affidavit showing compliance with the provisions of Minnesota Statue 290.92 requiring withholding state income tax).
2. Waiver of Mechanic's Lien Rights (Affidavits that all claims against contractor, A & B Construction LTD, by reasons of the contract have been fully paid or satisfactorily secured).
Following receipt of these items, final payment will be issued.
1. IC-134 (Contractor's Withholding Affidavit showing compliance with the provisions of Minnesota Statue 290.92 requiring withholding state income tax).
2. Waiver of Mechanic's Lien Rights (Affidavits that all claims against contractor, A & B Construction LTD, by reasons of the contract have been fully paid or satisfactorily secured).
Following receipt of these items, final payment will be issued.
Recommendation:
The Senior Engineering Technician has inspected the completed work and recommends final payment to A & B Construction LTD of Harper Iowa, for Improvement Project #22-10, Public Works Salt Shed, in the amount of $24,826.50.
Action:
Motion to adopt Resolution #23-224 approving final payment to A & B Construction LTD for IP #22-10, Public Works Salt Shed in the amount of $24,826.50.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 11/22/2023 01:35 PM |
| Brian Hagen | Brian Hagen | 11/22/2023 02:07 PM |
- Form Started By:
- Stacie Damjanovich
- Started On:
- 09/28/2023 09:44 AM
- Final Approval Date:
- 11/22/2023