6.1.
| Meeting Date: |
11/21/2023 |
| |
|
| Primary Strategic Plan Initiative: |
{ud_pd8} |
Title:
Receive Updates on Improvement Projects, Studies and Items of Interest
Purpose/Background:
Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.
City Improvement Projects
- 2024 PMP Projects
- Design in progress on 9 projects
- Conducting open houses
- 161st Avenue Reconstruction (IP #23-01)
- Construction substantially complete
- Punch list work in progress
- Central Park Parking Lot Reconstruction (IP #23-02)
- Construction substantially complete
- Punch list work in progress
- 167th Avenue Reconstruction (IP #23-04)
- Construction substantially complete
- Punch list work in progress
- Barthels Rum River Acres 2nd Reconstruction (IP #23-05)
- Construction substantially complete
- Punch list work in progress
- 2023 MSA Pavement Overlay Improvements (IP #23-06)
- Construction substantially complete
- Punch list work in progress
- Whispering Pines Estates Plat 3 Reconstructions (IP #23-10)
- Construction substantially complete
- Punch list work in progress
- Trott Brook Crossing Sanitary Sewer Lift Station Improvements (IP #23-11)
- Construction substantially complete
- Punch list work in progress
- HY-10 Ramsey Improvements (IP #23-12)
- Construction substantially complete
- Punch list work in progress
- COR Mass Grading (IP #23-20)
- Approximately 90% complete
- Completion anticipated December 2023
- Highway 47 Sound Wall north of Xkimo Street (IP #22-17)
- MnDOT Cooperative Construction Agreement required
- Staff anticipates requesting Council approval to authorize bids Spring/Summer 2024
- WTP Trunk Watermain Improvements (#21-08)
- Centralized Water Treatment Plant (#21-09)
- Construction in progress
- Substantial completion scheduled for May 1, 2025
- Final completion scheduled for August 1, 2025
- Ramsey Gateway Highway 10 Improvements (IP #20-11)
- Riverdale Drive east of SLB & temporary US 10 widening work nearly complete
- Ames Construction awarded contract October 11, 2023
- Construction in progress
- Final completion anticipated June 2026
City of Anoka Improvement Projects
- Highway 47 Corridor Improvements
- 3-lane design proposed south of Bunker Lake Boulevard
- City received regional solicitation funds for 2027 construction
- Signal system at McKinley Street is proposed to be permanent
- Anoka webpage https://clients.bolton-menk.com/anokahwy47/
Anoka County Improvement Projects
- 2024 Pavement Overlay Improvements
- Plans and specifications are being prepared
- Staff anticipates receiving plans for review soon
MnDOT Improvement Projects
- Anoka Solution Highway 10 Improvements
- US 10 / 169 & Ferry Street / TH 47 Interchange
- Ferry Street / Trunk Highway 47 Grade Separation @ BNSF Rail Crossing
- Rum River Bridge Replacement
Studies & Items of Interest
- Commercial/Industrial/Residential Developments
- Staff will respond to questions as needed
- Elk River Highway 10 Corridor Study
|
Notification:
N/A
Time Frame/Observations/Alternatives:
Staff estimates up to 10 minutes will be needed for updates and discussion.
Funding Source:
N/A
Recommendation:
N/A
Outcome/Action:
No formal action required. For Committee review and discussion purposes only.
Attachments
No file(s) attached.
Form Review
| Inbox |
Reviewed By |
Date |
| Brian Hagen |
Brian Hagen |
11/16/2023 02:32 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 11/16/2023 10:20 AM
- Final Approval Date:
- 11/16/2023